Park Lane By Heilbronn construction progress

The register lists Park Lane By Heilbronn in Jumeirah Village Circle as complete, with a registered completion date of February 2025. Its last site inspection on record was in February 2025. The developer is Heilbronn Properties Development.

100%

Built, at the site inspection of 14 February 2025

Construction complete

Registered completion date
February 2025
Construction started
February 2023
First registered
May 2024
Developer
Heilbronn Properties Development
Units
82
Escrow bank
Dubai Islamic Bank
Name in Arabic
بارك لاين من هيل برون
Project number
2940
Site inspections
3

Schedule

The register lists Park Lane By Heilbronn as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 February 2025

100%+8.8 pts

  • Park Lane By Heilbronn construction site, inspection photo 1, 14 February 2025
  • Park Lane By Heilbronn construction site, inspection photo 2, 14 February 2025
  • Park Lane By Heilbronn construction site, inspection photo 3, 14 February 2025
  • Park Lane By Heilbronn construction site, inspection photo 4, 14 February 2025

18 September 2024

91%+41 pts

  • Park Lane By Heilbronn construction site, inspection photo 1, 18 September 2024
  • Park Lane By Heilbronn construction site, inspection photo 2, 18 September 2024
  • Park Lane By Heilbronn construction site, inspection photo 3, 18 September 2024
  • Park Lane By Heilbronn construction site, inspection photo 4, 18 September 2024

4 March 2024

51%

  • Park Lane By Heilbronn construction site, inspection photo 1, 4 March 2024
  • Park Lane By Heilbronn construction site, inspection photo 2, 4 March 2024
  • Park Lane By Heilbronn construction site, inspection photo 3, 4 March 2024
  • Park Lane By Heilbronn construction site, inspection photo 4, 4 March 2024

All 30 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Park Lane By Heilbronn?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Park Lane By Heilbronn handover date?
Construction of Park Lane By Heilbronn is recorded as complete, with a registered completion date of February 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Park Lane By Heilbronn?
Park Lane By Heilbronn was 100% built at the site inspection on 14 February 2025. The site has been inspected 3 times since March 2024. The Land Department took 30 site photos at its inspections.
Is Park Lane By Heilbronn delayed?
The register lists construction as complete.
Who is building Park Lane By Heilbronn?
The registered developer is Heilbronn Properties Development.
Which bank holds the escrow account for Park Lane By Heilbronn?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.