Pantheon Elysee construction progress

The register lists Pantheon Elysee in Jumeirah Village Circle as complete, with a registered completion date of January 2021. Its last site inspection on record was in January 2021. The developer is Pantheon Real Estate Development.

100%

Built, at the site inspection of 4 January 2021

Construction complete

Registered completion date
January 2021
Construction started
April 2018
First registered
November 2018
Developer
Pantheon Real Estate Development
Units
272
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بانثيون اليسي
Project number
1988
Site inspections
7

Schedule

The register lists Pantheon Elysee as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 January 2021

100%+15 pts

  • Pantheon Elysee construction site, inspection photo 1, 4 January 2021
  • Pantheon Elysee construction site, inspection photo 2, 4 January 2021
  • Pantheon Elysee construction site, inspection photo 3, 4 January 2021
  • Pantheon Elysee construction site, inspection photo 4, 4 January 2021

8 October 2020

85%+17 pts

  • Pantheon Elysee construction site, inspection photo 1, 8 October 2020
  • Pantheon Elysee construction site, inspection photo 2, 8 October 2020
  • Pantheon Elysee construction site, inspection photo 3, 8 October 2020
  • Pantheon Elysee construction site, inspection photo 4, 8 October 2020

27 May 2020

68%+8.1 pts

  • Pantheon Elysee construction site, inspection photo 1, 27 May 2020
  • Pantheon Elysee construction site, inspection photo 2, 27 May 2020
  • Pantheon Elysee construction site, inspection photo 3, 27 May 2020
  • Pantheon Elysee construction site, inspection photo 4, 27 May 2020

5 March 2020

60%+29 pts

  • Pantheon Elysee construction site, inspection photo 1, 5 March 2020
  • Pantheon Elysee construction site, inspection photo 2, 5 March 2020
  • Pantheon Elysee construction site, inspection photo 3, 5 March 2020
  • Pantheon Elysee construction site, inspection photo 4, 5 March 2020

8 September 2019

31%+18 pts

  • Pantheon Elysee construction site, inspection photo 1, 8 September 2019
  • Pantheon Elysee construction site, inspection photo 2, 8 September 2019
  • Pantheon Elysee construction site, inspection photo 3, 8 September 2019
  • Pantheon Elysee construction site, inspection photo 4, 8 September 2019

28 February 2019

13%+10 pts

  • Pantheon Elysee construction site, inspection photo 1, 28 February 2019
  • Pantheon Elysee construction site, inspection photo 2, 28 February 2019
  • Pantheon Elysee construction site, inspection photo 3, 28 February 2019
  • Pantheon Elysee construction site, inspection photo 4, 28 February 2019

4 September 2018

3.3%

  • Pantheon Elysee construction site, inspection photo 1, 4 September 2018
  • Pantheon Elysee construction site, inspection photo 2, 4 September 2018
  • Pantheon Elysee construction site, inspection photo 3, 4 September 2018
  • Pantheon Elysee construction site, inspection photo 4, 4 September 2018

All 63 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Pantheon Elysee?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Pantheon Elysee handover date?
Construction of Pantheon Elysee is recorded as complete, with a registered completion date of January 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Pantheon Elysee?
Pantheon Elysee was 100% built at the site inspection on 4 January 2021. The site has been inspected 7 times since September 2018. The Land Department took 63 site photos at its inspections.
Is Pantheon Elysee delayed?
The register lists construction as complete.
Who is building Pantheon Elysee?
The registered developer is Pantheon Real Estate Development.
Which bank holds the escrow account for Pantheon Elysee?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.