Olivo Park Residences By Evera construction progress

The register lists Olivo Park Residences By Evera in Jumeirah Village Circle as complete, with a registered completion date of December 2025. Its last site inspection on record was in April 2026. The developer is Evera Real Estate Development Co.

100%

Built, at the site inspection of 24 April 2026

Construction complete

Registered completion date
December 2025
Construction started
September 2023
First registered
November 2024
Developer
Evera Real Estate Development Co
Units
122
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
Olivo Park Residences By Evera
Project number
3338
Site inspections
5

Schedule

The register lists Olivo Park Residences By Evera as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 April 2026

100%+33 pts

  • Olivo Park Residences By Evera construction site, inspection photo 1, 24 April 2026
  • Olivo Park Residences By Evera construction site, inspection photo 2, 24 April 2026
  • Olivo Park Residences By Evera construction site, inspection photo 3, 24 April 2026
  • Olivo Park Residences By Evera construction site, inspection photo 4, 24 April 2026

31 July 2025

67%+11 pts

  • Olivo Park Residences By Evera construction site, inspection photo 1, 31 July 2025
  • Olivo Park Residences By Evera construction site, inspection photo 2, 31 July 2025
  • Olivo Park Residences By Evera construction site, inspection photo 3, 31 July 2025
  • Olivo Park Residences By Evera construction site, inspection photo 4, 31 July 2025

25 April 2025

56%+5.6 pts

  • Olivo Park Residences By Evera construction site, inspection photo 1, 25 April 2025
  • Olivo Park Residences By Evera construction site, inspection photo 2, 25 April 2025
  • Olivo Park Residences By Evera construction site, inspection photo 3, 25 April 2025
  • Olivo Park Residences By Evera construction site, inspection photo 4, 25 April 2025

28 January 2025

50%+9.8 pts

  • Olivo Park Residences By Evera construction site, inspection photo 1, 28 January 2025
  • Olivo Park Residences By Evera construction site, inspection photo 2, 28 January 2025
  • Olivo Park Residences By Evera construction site, inspection photo 3, 28 January 2025
  • Olivo Park Residences By Evera construction site, inspection photo 4, 28 January 2025

18 October 2024

41%

  • Olivo Park Residences By Evera construction site, inspection photo 1, 18 October 2024
  • Olivo Park Residences By Evera construction site, inspection photo 2, 18 October 2024
  • Olivo Park Residences By Evera construction site, inspection photo 3, 18 October 2024
  • Olivo Park Residences By Evera construction site, inspection photo 4, 18 October 2024

All 45 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Olivo Park Residences By Evera?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Olivo Park Residences By Evera handover date?
Construction of Olivo Park Residences By Evera is recorded as complete, with a registered completion date of December 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Olivo Park Residences By Evera?
Olivo Park Residences By Evera was 100% built at the site inspection on 24 April 2026. The site has been inspected 5 times since October 2024. The Land Department took 45 site photos at its inspections.
Is Olivo Park Residences By Evera delayed?
The register lists construction as complete.
Who is building Olivo Park Residences By Evera?
The registered developer is Evera Real Estate Development Co.
Which bank holds the escrow account for Olivo Park Residences By Evera?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.