Oakyard Residences construction progress
The registered completion date for Oakyard Residences in Jumeirah Village Circle is February 2027. At the last site inspection, in June 2026, it was 26% built. The developer is One Yard Real Estate Development.
26%
Built, at the site inspection of 25 June 2026
Running behind its date
- Registered completion date
- February 2027
- Finish at recent pace
- November 2028
- Construction started
- September 2024
- First registered
- February 2025
- Developer
- One Yard Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 191
- Escrow bank
- Mashreq Bank
- Name in Arabic
- اوكيارد رزيدنسز
- Project number
- 3473
- Site inspections
- 4
Schedule
Between December 2025 and June 2026 the site added about 2.6 points a month. At that rate it would finish around November 2028, more than three months after its registered date of February 2027.
Site inspections
25 June 2026
26%+9.1 pts
16 March 2026
17%+7.5 pts
11 December 2025
9.6%+7.3 pts
10 January 2025
2.3%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Oakyard Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Oakyard Residences handover date?
- The registered completion date is February 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Oakyard Residences?
- Oakyard Residences was 26% built at the site inspection on 25 June 2026. The site has been inspected 4 times since January 2025. The Land Department took 20 site photos at its inspections.
- Is Oakyard Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
- Who is building Oakyard Residences?
- The registered developer is One Yard Real Estate Development.
- Which bank holds the escrow account for Oakyard Residences?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)