The registered completion date for Oakyard Residences in Jumeirah Village Circle is February 2027. At the last site inspection, in June 2026, it was 26% built. The developer is One Yard Real Estate Development.

26%

Built, at the site inspection of 25 June 2026

Running behind its date

Registered completion date
February 2027
Finish at recent pace
November 2028
Construction started
September 2024
First registered
February 2025
Developer
One Yard Real Estate Development
Units
191
Escrow bank
Mashreq Bank
Name in Arabic
اوكيارد رزيدنسز
Project number
3473
Site inspections
4

Schedule

Between December 2025 and June 2026 the site added about 2.6 points a month. At that rate it would finish around November 2028, more than three months after its registered date of February 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 June 2026

26%+9.1 pts

  • Oakyard Residences construction site, inspection photo 1, 25 June 2026
  • Oakyard Residences construction site, inspection photo 2, 25 June 2026
  • Oakyard Residences construction site, inspection photo 3, 25 June 2026
  • Oakyard Residences construction site, inspection photo 4, 25 June 2026

16 March 2026

17%+7.5 pts

  • Oakyard Residences construction site, inspection photo 1, 16 March 2026
  • Oakyard Residences construction site, inspection photo 2, 16 March 2026
  • Oakyard Residences construction site, inspection photo 3, 16 March 2026
  • Oakyard Residences construction site, inspection photo 4, 16 March 2026

11 December 2025

9.6%+7.3 pts

  • Oakyard Residences construction site, inspection photo 1, 11 December 2025
  • Oakyard Residences construction site, inspection photo 2, 11 December 2025
  • Oakyard Residences construction site, inspection photo 3, 11 December 2025
  • Oakyard Residences construction site, inspection photo 4, 11 December 2025

10 January 2025

2.3%

  • Oakyard Residences construction site, inspection photo 1, 10 January 2025
  • Oakyard Residences construction site, inspection photo 2, 10 January 2025
  • Oakyard Residences construction site, inspection photo 3, 10 January 2025
  • Oakyard Residences construction site, inspection photo 4, 10 January 2025

All 20 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Oakyard Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Oakyard Residences handover date?
The registered completion date is February 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Oakyard Residences?
Oakyard Residences was 26% built at the site inspection on 25 June 2026. The site has been inspected 4 times since January 2025. The Land Department took 20 site photos at its inspections.
Is Oakyard Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
Who is building Oakyard Residences?
The registered developer is One Yard Real Estate Development.
Which bank holds the escrow account for Oakyard Residences?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.