Skip to content

North Forty Three Serviced Residences construction progress

North Forty Three Serviced Residences in Jumeirah Village Circle is 95% built at the Land Department inspection of April 2026. Developer North Forty Three Real Estate Development. Completion registered for July 2024.

95%

Built, at the Land Department site inspection of 14 April 2026

26 months past its registered completion date

Completion date (Land Department)
July 2024
Finish at recent pace
July 2026
Construction started
March 2021
Registered with the Land Department
November 2022
Developer
North Forty Three Real Estate Development
Units
229
Escrow bank
First Abu Dhabi Bank
Name in Arabic
نورث فورتي ثري سيرفيسد ريزيدنسيز
Land Department project number
2435
Land Department site inspections
10

Schedule

North Forty Three Serviced Residences was registered to complete in July 2024, 26 months ago, and is still under construction. Over the last year of inspections it has added about 1.5 points a month. Kept at that rate, the site would reach 100% around July 2026.

0%25%50%75%100%20222023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 April 2026

95%+4.7 pts

  • North Forty Three Serviced Residences construction site, Land Department inspection photo 1, 14 April 2026
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 2, 14 April 2026
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 3, 14 April 2026
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 4, 14 April 2026

11 December 2025

90%+8.0 pts

  • North Forty Three Serviced Residences construction site, Land Department inspection photo 1, 11 December 2025
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 2, 11 December 2025
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 3, 11 December 2025
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 4, 11 December 2025

1 August 2025

82%+7.2 pts

  • North Forty Three Serviced Residences construction site, Land Department inspection photo 1, 1 August 2025
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 2, 1 August 2025
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 3, 1 August 2025
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 4, 1 August 2025

15 March 2025

75%+4.7 pts

  • North Forty Three Serviced Residences construction site, Land Department inspection photo 1, 15 March 2025
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 2, 15 March 2025
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 3, 15 March 2025
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 4, 15 March 2025

12 January 2025

70%+20 pts

  • North Forty Three Serviced Residences construction site, Land Department inspection photo 1, 12 January 2025
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 2, 12 January 2025
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 3, 12 January 2025
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 4, 12 January 2025

3 September 2024

50%+5.8 pts

  • North Forty Three Serviced Residences construction site, Land Department inspection photo 1, 3 September 2024
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 2, 3 September 2024
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 3, 3 September 2024
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 4, 3 September 2024

26 April 2024

44%+7.8 pts

  • North Forty Three Serviced Residences construction site, Land Department inspection photo 1, 26 April 2024
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 2, 26 April 2024
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 3, 26 April 2024
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 4, 26 April 2024

15 August 2023

36%+7.7 pts

  • North Forty Three Serviced Residences construction site, Land Department inspection photo 1, 15 August 2023
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 2, 15 August 2023
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 3, 15 August 2023
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 4, 15 August 2023

22 February 2023

29%+2.4 pts

  • North Forty Three Serviced Residences construction site, Land Department inspection photo 1, 22 February 2023
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 2, 22 February 2023
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 3, 22 February 2023
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 4, 22 February 2023

10 August 2022

26%

  • North Forty Three Serviced Residences construction site, Land Department inspection photo 1, 10 August 2022
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 2, 10 August 2022
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 3, 10 August 2022
  • North Forty Three Serviced Residences construction site, Land Department inspection photo 4, 10 August 2022

All 88 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Own a unit in North Forty Three Serviced Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will North Forty Three Serviced Residences be completed?
The completion date registered with the Dubai Land Department is July 2024. At the pace of its recent inspections the site would reach 100% around July 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of North Forty Three Serviced Residences is built?
95%, measured at the Land Department site inspection on 14 April 2026. The Land Department engineers have inspected the site 10 times since August 2022.
Is North Forty Three Serviced Residences delayed?
Yes. Its registered completion date of July 2024 has passed and the Land Department still lists it as under construction.
Who is building North Forty Three Serviced Residences?
The registered developer is North Forty Three Real Estate Development.
Which bank holds the escrow account for North Forty Three Serviced Residences?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.