North Forty Three Serviced Residences construction progress
North Forty Three Serviced Residences in Jumeirah Village Circle is 95% built at the Land Department inspection of April 2026. Developer North Forty Three Real Estate Development. Completion registered for July 2024.
95%
Built, at the Land Department site inspection of 14 April 2026
26 months past its registered completion date
- Completion date (Land Department)
- July 2024
- Finish at recent pace
- July 2026
- Construction started
- March 2021
- Registered with the Land Department
- November 2022
- Developer
- North Forty Three Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 229
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- نورث فورتي ثري سيرفيسد ريزيدنسيز
- Land Department project number
- 2435
- Land Department site inspections
- 10
Schedule
North Forty Three Serviced Residences was registered to complete in July 2024, 26 months ago, and is still under construction. Over the last year of inspections it has added about 1.5 points a month. Kept at that rate, the site would reach 100% around July 2026.
Site inspections
14 April 2026
95%+4.7 pts
11 December 2025
90%+8.0 pts
1 August 2025
82%+7.2 pts
15 March 2025
75%+4.7 pts
12 January 2025
70%+20 pts
3 September 2024
50%+5.8 pts
26 April 2024
44%+7.8 pts
15 August 2023
36%+7.7 pts
22 February 2023
29%+2.4 pts
10 August 2022
26%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Own a unit in North Forty Three Serviced Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will North Forty Three Serviced Residences be completed?
- The completion date registered with the Dubai Land Department is July 2024. At the pace of its recent inspections the site would reach 100% around July 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of North Forty Three Serviced Residences is built?
- 95%, measured at the Land Department site inspection on 14 April 2026. The Land Department engineers have inspected the site 10 times since August 2022.
- Is North Forty Three Serviced Residences delayed?
- Yes. Its registered completion date of July 2024 has passed and the Land Department still lists it as under construction.
- Who is building North Forty Three Serviced Residences?
- The registered developer is North Forty Three Real Estate Development.
- Which bank holds the escrow account for North Forty Three Serviced Residences?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)









.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)


.jpg&w=3840&q=75)
.jpg&w=3840&q=75)