Lolena construction progress

The register lists Lolena in Jumeirah Village Circle as complete, with a registered completion date of July 2019. Its last site inspection on record was in September 2019. The developer is Al Masarat Real Estate Development.

100%

Built, at the site inspection of 4 September 2019

Construction complete

Registered completion date
July 2019
Construction started
May 2009
First registered
November 2008
Developer
Al Masarat Real Estate Development
Units
97
Escrow bank
Mashreq Bank
Name in Arabic
لولينا
Project number
249
Site inspections
14

Schedule

The register lists Lolena as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20102012201420162018
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 September 2019

100%+3.0 pts

  • Lolena construction site, inspection photo 1, 4 September 2019
  • Lolena construction site, inspection photo 2, 4 September 2019
  • Lolena construction site, inspection photo 3, 4 September 2019
  • Lolena construction site, inspection photo 4, 4 September 2019

6 August 2018

97%+4.4 pts

  • Lolena construction site, inspection photo 1, 6 August 2018
  • Lolena construction site, inspection photo 2, 6 August 2018
  • Lolena construction site, inspection photo 3, 6 August 2018
  • Lolena construction site, inspection photo 4, 6 August 2018

13 November 2017

93%+2.4 pts

  • Lolena construction site, inspection photo 1, 13 November 2017
  • Lolena construction site, inspection photo 2, 13 November 2017
  • Lolena construction site, inspection photo 3, 13 November 2017
  • Lolena construction site, inspection photo 4, 13 November 2017

28 September 2017

90%+4.9 pts

  • Lolena construction site, inspection photo 1, 28 September 2017
  • Lolena construction site, inspection photo 2, 28 September 2017
  • Lolena construction site, inspection photo 3, 28 September 2017
  • Lolena construction site, inspection photo 4, 28 September 2017

15 May 2017

85%+5.2 pts

  • Lolena construction site, inspection photo 1, 15 May 2017
  • Lolena construction site, inspection photo 2, 15 May 2017
  • Lolena construction site, inspection photo 3, 15 May 2017
  • Lolena construction site, inspection photo 4, 15 May 2017

15 January 2017

80%+1.5 pts

  • Lolena construction site, inspection photo 1, 15 January 2017
  • Lolena construction site, inspection photo 2, 15 January 2017
  • Lolena construction site, inspection photo 3, 15 January 2017
  • Lolena construction site, inspection photo 4, 15 January 2017

9 October 2016

79%+1.5 pts

  • Lolena construction site, inspection photo 1, 9 October 2016
  • Lolena construction site, inspection photo 2, 9 October 2016
  • Lolena construction site, inspection photo 3, 9 October 2016
  • Lolena construction site, inspection photo 4, 9 October 2016

9 February 2016

77%+7.0 pts

  • Lolena construction site, inspection photo 1, 9 February 2016
  • Lolena construction site, inspection photo 2, 9 February 2016
  • Lolena construction site, inspection photo 3, 9 February 2016
  • Lolena construction site, inspection photo 4, 9 February 2016

4 May 2015

70%+2.9 pts

  • Lolena construction site, inspection photo 1, 4 May 2015
  • Lolena construction site, inspection photo 2, 4 May 2015
  • Lolena construction site, inspection photo 3, 4 May 2015
  • Lolena construction site, inspection photo 4, 4 May 2015

23 February 2015

67%+6.8 pts

  • Lolena construction site, inspection photo 1, 23 February 2015
  • Lolena construction site, inspection photo 2, 23 February 2015
  • Lolena construction site, inspection photo 3, 23 February 2015
  • Lolena construction site, inspection photo 4, 23 February 2015

All 144 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Lolena?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Lolena handover date?
Construction of Lolena is recorded as complete, with a registered completion date of July 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Lolena?
Lolena was 100% built at the site inspection on 4 September 2019. The site has been inspected 14 times since July 2012. The Land Department took 144 site photos at its inspections.
Is Lolena delayed?
The register lists construction as complete.
Who is building Lolena?
The registered developer is Al Masarat Real Estate Development.
Which bank holds the escrow account for Lolena?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.