La Perla Homes 12 construction progress

The register lists La Perla Homes 12 in Jumeirah Village Circle as complete, with a registered completion date of January 2024. Its last site inspection on record was in February 2025. The developer is G H D Real Estate Development.

100%

Built, at the site inspection of 26 February 2025

Construction complete

Registered completion date
January 2024
Construction started
September 2022
First registered
March 2023
Developer
G H D Real Estate Development
Units
18
Escrow bank
First Abu Dhabi Bank
Name in Arabic
لا بيرلا هومز 12
Project number
2463
Site inspections
4

Schedule

The register lists La Perla Homes 12 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

26 February 2025

100%+37 pts

  • La Perla Homes 12 construction site, inspection photo 1, 26 February 2025
  • La Perla Homes 12 construction site, inspection photo 2, 26 February 2025
  • La Perla Homes 12 construction site, inspection photo 3, 26 February 2025
  • La Perla Homes 12 construction site, inspection photo 4, 26 February 2025

2 March 2024

63%+21 pts

  • La Perla Homes 12 construction site, inspection photo 1, 2 March 2024
  • La Perla Homes 12 construction site, inspection photo 2, 2 March 2024
  • La Perla Homes 12 construction site, inspection photo 3, 2 March 2024
  • La Perla Homes 12 construction site, inspection photo 4, 2 March 2024

26 September 2023

42%+42 pts

  • La Perla Homes 12 construction site, inspection photo 1, 26 September 2023
  • La Perla Homes 12 construction site, inspection photo 2, 26 September 2023
  • La Perla Homes 12 construction site, inspection photo 3, 26 September 2023
  • La Perla Homes 12 construction site, inspection photo 4, 26 September 2023

10 October 2022

0%

  • La Perla Homes 12 construction site, inspection photo 1, 10 October 2022
  • La Perla Homes 12 construction site, inspection photo 2, 10 October 2022
  • La Perla Homes 12 construction site, inspection photo 3, 10 October 2022

All 32 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in La Perla Homes 12?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the La Perla Homes 12 handover date?
Construction of La Perla Homes 12 is recorded as complete, with a registered completion date of January 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on La Perla Homes 12?
La Perla Homes 12 was 100% built at the site inspection on 26 February 2025. The site has been inspected 4 times since October 2022. The Land Department took 32 site photos at its inspections.
Is La Perla Homes 12 delayed?
The register lists construction as complete.
Who is building La Perla Homes 12?
The registered developer is G H D Real Estate Development.
Which bank holds the escrow account for La Perla Homes 12?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.