Knight Bridge Court & Kensngton Manor construction progress

The register lists Knight Bridge Court & Kensngton Manor in Jumeirah Village Circle as complete, with a registered completion date of July 2015. Its last site inspection on record was in March 2016. The developer is Acw Holding Ltd.

100%

Built, at the site inspection of 1 March 2016

Construction complete

Registered completion date
July 2015
Construction started
January 2009
First registered
November 2008
Developer
Acw Holding Ltd
Units
308
Escrow bank
Dubai Islamic Bank
Name in Arabic
نايت بريدج كورت آند كينسنجتون مانور
Project number
637
Site inspections
5

Schedule

The register lists Knight Bridge Court & Kensngton Manor as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2010201220142016
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 March 2016

100%+2.0 pts

  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 1, 1 March 2016
  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 2, 1 March 2016
  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 3, 1 March 2016
  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 4, 1 March 2016

8 September 2015

98%+6.4 pts

  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 1, 8 September 2015
  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 2, 8 September 2015
  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 3, 8 September 2015
  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 4, 8 September 2015

27 January 2014

92%+11 pts

  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 1, 27 January 2014
  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 2, 27 January 2014
  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 3, 27 January 2014
  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 4, 27 January 2014

23 May 2013

80%+9.3 pts

  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 1, 23 May 2013
  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 2, 23 May 2013
  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 3, 23 May 2013
  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 4, 23 May 2013

13 November 2012

71%

  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 1, 13 November 2012
  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 2, 13 November 2012
  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 3, 13 November 2012
  • Knight Bridge Court & Kensngton Manor construction site, inspection photo 4, 13 November 2012

All 56 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Knight Bridge Court & Kensngton Manor?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Knight Bridge Court & Kensngton Manor handover date?
Construction of Knight Bridge Court & Kensngton Manor is recorded as complete, with a registered completion date of July 2015. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Knight Bridge Court & Kensngton Manor?
Knight Bridge Court & Kensngton Manor was 100% built at the site inspection on 1 March 2016. The site has been inspected 5 times since November 2012. The Land Department took 56 site photos at its inspections.
Is Knight Bridge Court & Kensngton Manor delayed?
The register lists construction as complete.
Who is building Knight Bridge Court & Kensngton Manor?
The registered developer is Acw Holding Ltd.
Which bank holds the escrow account for Knight Bridge Court & Kensngton Manor?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.