Indigo Ville 8 construction progress

The register lists Indigo Ville 8 in Jumeirah Village Circle as complete, with a registered completion date of July 2016. Its last site inspection on record was in November 2016. The developer is Venus Properties Investment Ltd.

100%

Built, at the site inspection of 10 November 2016

Construction complete

Registered completion date
July 2016
Construction started
August 2013
First registered
November 2008
Developer
Venus Properties Investment Ltd
Units
18
Escrow bank
Mashreq Bank
Name in Arabic
إنديغو فيل 8
Project number
693
Site inspections
7

Schedule

The register lists Indigo Ville 8 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201420152016
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 November 2016

100%+6.0 pts

  • Indigo Ville 8 construction site, inspection photo 1, 10 November 2016
  • Indigo Ville 8 construction site, inspection photo 2, 10 November 2016
  • Indigo Ville 8 construction site, inspection photo 3, 10 November 2016
  • Indigo Ville 8 construction site, inspection photo 4, 10 November 2016

21 December 2015

94%+48 pts

  • Indigo Ville 8 construction site, inspection photo 1, 21 December 2015
  • Indigo Ville 8 construction site, inspection photo 2, 21 December 2015
  • Indigo Ville 8 construction site, inspection photo 3, 21 December 2015
  • Indigo Ville 8 construction site, inspection photo 4, 21 December 2015

2 March 2015

46%+22 pts

  • Indigo Ville 8 construction site, inspection photo 1, 2 March 2015
  • Indigo Ville 8 construction site, inspection photo 2, 2 March 2015
  • Indigo Ville 8 construction site, inspection photo 3, 2 March 2015
  • Indigo Ville 8 construction site, inspection photo 4, 2 March 2015

30 November 2014

25%+21 pts

  • Indigo Ville 8 construction site, inspection photo 1, 30 November 2014
  • Indigo Ville 8 construction site, inspection photo 2, 30 November 2014
  • Indigo Ville 8 construction site, inspection photo 3, 30 November 2014
  • Indigo Ville 8 construction site, inspection photo 4, 30 November 2014

19 August 2014

4.0%+3.5 pts

  • Indigo Ville 8 construction site, inspection photo 1, 19 August 2014
  • Indigo Ville 8 construction site, inspection photo 2, 19 August 2014
  • Indigo Ville 8 construction site, inspection photo 3, 19 August 2014
  • Indigo Ville 8 construction site, inspection photo 4, 19 August 2014

4 February 2014

0.5%

  • Indigo Ville 8 construction site, inspection photo 1, 4 February 2014
  • Indigo Ville 8 construction site, inspection photo 2, 4 February 2014
  • Indigo Ville 8 construction site, inspection photo 3, 4 February 2014
  • Indigo Ville 8 construction site, inspection photo 4, 4 February 2014

30 September 2013

0.5%

  • Indigo Ville 8 construction site, inspection photo 1, 30 September 2013
  • Indigo Ville 8 construction site, inspection photo 2, 30 September 2013
  • Indigo Ville 8 construction site, inspection photo 3, 30 September 2013
  • Indigo Ville 8 construction site, inspection photo 4, 30 September 2013

All 51 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Indigo Ville 8?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Indigo Ville 8 handover date?
Construction of Indigo Ville 8 is recorded as complete, with a registered completion date of July 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Indigo Ville 8?
Indigo Ville 8 was 100% built at the site inspection on 10 November 2016. The site has been inspected 7 times since September 2013. The Land Department took 51 site photos at its inspections.
Is Indigo Ville 8 delayed?
The register lists construction as complete.
Who is building Indigo Ville 8?
The registered developer is Venus Properties Investment Ltd.
Which bank holds the escrow account for Indigo Ville 8?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.