Indigo Ville 3 construction progress

The register lists Indigo Ville 3 in Jumeirah Village Circle as complete, with a registered completion date of September 2013. Its last site inspection on record was in September 2013. The developer is Venus Properties Investment Ltd.

100%

Built, at the site inspection of 30 September 2013

Construction complete

Registered completion date
September 2013
Construction started
February 2010
First registered
November 2008
Developer
Venus Properties Investment Ltd
Units
18
Escrow bank
Mashreq Bank
Name in Arabic
إنديغو فيل 3
Project number
695
Site inspections
3

Schedule

The register lists Indigo Ville 3 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201120122013
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 September 2013

100%+32 pts

  • Indigo Ville 3 construction site, inspection photo 1, 30 September 2013
  • Indigo Ville 3 construction site, inspection photo 2, 30 September 2013
  • Indigo Ville 3 construction site, inspection photo 3, 30 September 2013
  • Indigo Ville 3 construction site, inspection photo 4, 30 September 2013

26 February 2013

68%+47 pts

  • Indigo Ville 3 construction site, inspection photo 1, 26 February 2013
  • Indigo Ville 3 construction site, inspection photo 2, 26 February 2013
  • Indigo Ville 3 construction site, inspection photo 3, 26 February 2013
  • Indigo Ville 3 construction site, inspection photo 4, 26 February 2013

1 August 2012

20%

  • Indigo Ville 3 construction site, inspection photo 1, 1 August 2012
  • Indigo Ville 3 construction site, inspection photo 2, 1 August 2012
  • Indigo Ville 3 construction site, inspection photo 3, 1 August 2012
  • Indigo Ville 3 construction site, inspection photo 4, 1 August 2012

All 22 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Indigo Ville 3?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Indigo Ville 3 handover date?
Construction of Indigo Ville 3 is recorded as complete, with a registered completion date of September 2013. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Indigo Ville 3?
Indigo Ville 3 was 100% built at the site inspection on 30 September 2013. The site has been inspected 3 times since August 2012. The Land Department took 22 site photos at its inspections.
Is Indigo Ville 3 delayed?
The register lists construction as complete.
Who is building Indigo Ville 3?
The registered developer is Venus Properties Investment Ltd.
Which bank holds the escrow account for Indigo Ville 3?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.