Hyati Avenue construction progress

The register lists Hyati Avenue in Jumeirah Village Circle as complete, with a registered completion date of March 2020. Its last site inspection on record was in March 2020. The developer is Aurora Real Estate Development.

100%

Built, at the site inspection of 9 March 2020

Construction complete

Registered completion date
March 2020
Construction started
November 2017
First registered
January 2019
Developer
Aurora Real Estate Development
Units
122
Escrow bank
Dubai Islamic Bank
Name in Arabic
حياتى أفينيو
Project number
2108
Site inspections
5

Schedule

The register lists Hyati Avenue as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 March 2020

100%+18 pts

  • Hyati Avenue construction site, inspection photo 1, 9 March 2020
  • Hyati Avenue construction site, inspection photo 2, 9 March 2020
  • Hyati Avenue construction site, inspection photo 3, 9 March 2020
  • Hyati Avenue construction site, inspection photo 4, 9 March 2020

12 December 2019

82%+22 pts

  • Hyati Avenue construction site, inspection photo 1, 12 December 2019
  • Hyati Avenue construction site, inspection photo 2, 12 December 2019
  • Hyati Avenue construction site, inspection photo 3, 12 December 2019
  • Hyati Avenue construction site, inspection photo 4, 12 December 2019

22 August 2019

60%+18 pts

  • Hyati Avenue construction site, inspection photo 1, 22 August 2019
  • Hyati Avenue construction site, inspection photo 2, 22 August 2019
  • Hyati Avenue construction site, inspection photo 3, 22 August 2019
  • Hyati Avenue construction site, inspection photo 4, 22 August 2019

12 May 2019

42%+21 pts

  • Hyati Avenue construction site, inspection photo 1, 12 May 2019
  • Hyati Avenue construction site, inspection photo 2, 12 May 2019
  • Hyati Avenue construction site, inspection photo 3, 12 May 2019
  • Hyati Avenue construction site, inspection photo 4, 12 May 2019

26 December 2018

21%

  • Hyati Avenue construction site, inspection photo 1, 26 December 2018
  • Hyati Avenue construction site, inspection photo 2, 26 December 2018
  • Hyati Avenue construction site, inspection photo 3, 26 December 2018
  • Hyati Avenue construction site, inspection photo 4, 26 December 2018

All 52 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Hyati Avenue?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Hyati Avenue handover date?
Construction of Hyati Avenue is recorded as complete, with a registered completion date of March 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Hyati Avenue?
Hyati Avenue was 100% built at the site inspection on 9 March 2020. The site has been inspected 5 times since December 2018. The Land Department took 52 site photos at its inspections.
Is Hyati Avenue delayed?
The register lists construction as complete.
Who is building Hyati Avenue?
The registered developer is Aurora Real Estate Development.
Which bank holds the escrow account for Hyati Avenue?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.