Hillmont Residences By Ellington construction progress
The registered completion date for Hillmont Residences By Ellington in Jumeirah Village Circle is December 2026. At the last site inspection, in July 2026, it was 26% built. The developer is B L G Development.
26%
Built, at the site inspection of 22 July 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- August 2029
- Construction started
- May 2024
- First registered
- July 2024
- Developer
- B L G Development
- Community
- Jumeirah Village Circle
- Units
- 145
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- هيلمونت ريزيدنسز من إلينغتون
- Project number
- 3081
- Site inspections
- 5
Schedule
Between October 2025 and July 2026 the site added about 2.0 points a month. At that rate it would finish around August 2029, more than three months after its registered date of December 2026.
Site inspections
22 July 2026
26%+12 pts
26 March 2026
15%+6.5 pts
21 October 2025
8.2%+5.0 pts
25 June 2025
3.2%+3.2 pts
23 May 2024
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Hillmont Residences By Ellington?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Hillmont Residences By Ellington handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Hillmont Residences By Ellington?
- Hillmont Residences By Ellington was 26% built at the site inspection on 22 July 2026. The site has been inspected 5 times since May 2024. The Land Department took 27 site photos at its inspections.
- Is Hillmont Residences By Ellington delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Hillmont Residences By Ellington?
- The registered developer is B L G Development.
- Which bank holds the escrow account for Hillmont Residences By Ellington?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)