Hillmont Residences By Ellington construction progress

The registered completion date for Hillmont Residences By Ellington in Jumeirah Village Circle is December 2026. At the last site inspection, in July 2026, it was 26% built. The developer is B L G Development.

26%

Built, at the site inspection of 22 July 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
August 2029
Construction started
May 2024
First registered
July 2024
Developer
B L G Development
Units
145
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
هيلمونت ريزيدنسز من إلينغتون
Project number
3081
Site inspections
5

Schedule

Between October 2025 and July 2026 the site added about 2.0 points a month. At that rate it would finish around August 2029, more than three months after its registered date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 July 2026

26%+12 pts

  • Hillmont Residences By Ellington construction site, inspection photo 1, 22 July 2026
  • Hillmont Residences By Ellington construction site, inspection photo 2, 22 July 2026
  • Hillmont Residences By Ellington construction site, inspection photo 3, 22 July 2026
  • Hillmont Residences By Ellington construction site, inspection photo 4, 22 July 2026

26 March 2026

15%+6.5 pts

  • Hillmont Residences By Ellington construction site, inspection photo 1, 26 March 2026
  • Hillmont Residences By Ellington construction site, inspection photo 2, 26 March 2026
  • Hillmont Residences By Ellington construction site, inspection photo 3, 26 March 2026
  • Hillmont Residences By Ellington construction site, inspection photo 4, 26 March 2026

21 October 2025

8.2%+5.0 pts

  • Hillmont Residences By Ellington construction site, inspection photo 1, 21 October 2025
  • Hillmont Residences By Ellington construction site, inspection photo 2, 21 October 2025
  • Hillmont Residences By Ellington construction site, inspection photo 3, 21 October 2025

25 June 2025

3.2%+3.2 pts

  • Hillmont Residences By Ellington construction site, inspection photo 1, 25 June 2025
  • Hillmont Residences By Ellington construction site, inspection photo 2, 25 June 2025
  • Hillmont Residences By Ellington construction site, inspection photo 3, 25 June 2025
  • Hillmont Residences By Ellington construction site, inspection photo 4, 25 June 2025

23 May 2024

0%

  • Hillmont Residences By Ellington construction site, inspection photo 1, 23 May 2024
  • Hillmont Residences By Ellington construction site, inspection photo 2, 23 May 2024

All 27 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Hillmont Residences By Ellington?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Hillmont Residences By Ellington handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Hillmont Residences By Ellington?
Hillmont Residences By Ellington was 26% built at the site inspection on 22 July 2026. The site has been inspected 5 times since May 2024. The Land Department took 27 site photos at its inspections.
Is Hillmont Residences By Ellington delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Hillmont Residences By Ellington?
The registered developer is B L G Development.
Which bank holds the escrow account for Hillmont Residences By Ellington?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.