Hameni construction progress

The register lists Hameni in Jumeirah Village Circle as complete, with a registered completion date of April 2020. Its last site inspection on record was in April 2020. The developer is Zaya Living Real Estate Development.

100%

Built, at the site inspection of 5 April 2020

Construction complete

Registered completion date
April 2020
Construction started
August 2014
First registered
June 2014
Developer
Zaya Living Real Estate Development
Units
504
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
هامينى
Project number
1541
Site inspections
13

Schedule

The register lists Hameni as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201520172019
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 April 2020

100%+1.0 pts

  • Hameni construction site, inspection photo 1, 5 April 2020
  • Hameni construction site, inspection photo 2, 5 April 2020
  • Hameni construction site, inspection photo 3, 5 April 2020
  • Hameni construction site, inspection photo 4, 5 April 2020

2 March 2020

99%+0.5 pts

  • Hameni construction site, inspection photo 1, 2 March 2020
  • Hameni construction site, inspection photo 2, 2 March 2020
  • Hameni construction site, inspection photo 3, 2 March 2020
  • Hameni construction site, inspection photo 4, 2 March 2020

14 January 2020

99%+3.4 pts

  • Hameni construction site, inspection photo 1, 14 January 2020
  • Hameni construction site, inspection photo 2, 14 January 2020
  • Hameni construction site, inspection photo 3, 14 January 2020
  • Hameni construction site, inspection photo 4, 14 January 2020

7 October 2019

95%+5.1 pts

  • Hameni construction site, inspection photo 1, 7 October 2019
  • Hameni construction site, inspection photo 2, 7 October 2019
  • Hameni construction site, inspection photo 3, 7 October 2019
  • Hameni construction site, inspection photo 4, 7 October 2019

12 March 2019

90%+6.9 pts

  • Hameni construction site, inspection photo 1, 12 March 2019
  • Hameni construction site, inspection photo 2, 12 March 2019
  • Hameni construction site, inspection photo 3, 12 March 2019
  • Hameni construction site, inspection photo 4, 12 March 2019

26 June 2018

83%+3.0 pts

  • Hameni construction site, inspection photo 1, 26 June 2018
  • Hameni construction site, inspection photo 2, 26 June 2018
  • Hameni construction site, inspection photo 3, 26 June 2018
  • Hameni construction site, inspection photo 4, 26 June 2018

13 February 2018

80%+15 pts

  • Hameni construction site, inspection photo 1, 13 February 2018
  • Hameni construction site, inspection photo 2, 13 February 2018
  • Hameni construction site, inspection photo 3, 13 February 2018
  • Hameni construction site, inspection photo 4, 13 February 2018

18 October 2017

65%+15 pts

  • Hameni construction site, inspection photo 1, 18 October 2017
  • Hameni construction site, inspection photo 2, 18 October 2017
  • Hameni construction site, inspection photo 3, 18 October 2017
  • Hameni construction site, inspection photo 4, 18 October 2017

2 March 2017

51%+15 pts

  • Hameni construction site, inspection photo 1, 2 March 2017
  • Hameni construction site, inspection photo 2, 2 March 2017
  • Hameni construction site, inspection photo 3, 2 March 2017
  • Hameni construction site, inspection photo 4, 2 March 2017

26 September 2016

35%+9.4 pts

  • Hameni construction site, inspection photo 1, 26 September 2016
  • Hameni construction site, inspection photo 2, 26 September 2016
  • Hameni construction site, inspection photo 3, 26 September 2016
  • Hameni construction site, inspection photo 4, 26 September 2016

All 127 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Hameni?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Hameni handover date?
Construction of Hameni is recorded as complete, with a registered completion date of April 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Hameni?
Hameni was 100% built at the site inspection on 5 April 2020. The site has been inspected 13 times since July 2015. The Land Department took 127 site photos at its inspections.
Is Hameni delayed?
The register lists construction as complete.
Who is building Hameni?
The registered developer is Zaya Living Real Estate Development.
Which bank holds the escrow account for Hameni?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.