Ghalia construction progress

The register lists Ghalia in Jumeirah Village Circle as complete, with a registered completion date of March 2019. Its last site inspection on record was in March 2019. The developer is Damac Development.

100%

Built, at the site inspection of 28 March 2019

Construction complete

Registered completion date
March 2019
Construction started
June 2014
First registered
May 2014
Developer
Damac Development
Units
743
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
غالية
Project number
1505
Site inspections
13

Schedule

The register lists Ghalia as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20152016201720182019
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 March 2019

100%+5.1 pts

  • Ghalia construction site, inspection photo 1, 28 March 2019
  • Ghalia construction site, inspection photo 2, 28 March 2019
  • Ghalia construction site, inspection photo 3, 28 March 2019
  • Ghalia construction site, inspection photo 4, 28 March 2019

4 October 2018

95%+4.3 pts

  • Ghalia construction site, inspection photo 1, 4 October 2018
  • Ghalia construction site, inspection photo 2, 4 October 2018
  • Ghalia construction site, inspection photo 3, 4 October 2018
  • Ghalia construction site, inspection photo 4, 4 October 2018

30 May 2018

91%+8.5 pts

  • Ghalia construction site, inspection photo 1, 30 May 2018
  • Ghalia construction site, inspection photo 2, 30 May 2018
  • Ghalia construction site, inspection photo 3, 30 May 2018
  • Ghalia construction site, inspection photo 4, 30 May 2018

31 January 2018

82%+9.8 pts

  • Ghalia construction site, inspection photo 1, 31 January 2018
  • Ghalia construction site, inspection photo 2, 31 January 2018
  • Ghalia construction site, inspection photo 3, 31 January 2018
  • Ghalia construction site, inspection photo 4, 31 January 2018

27 September 2017

72%+8.6 pts

  • Ghalia construction site, inspection photo 1, 27 September 2017
  • Ghalia construction site, inspection photo 2, 27 September 2017
  • Ghalia construction site, inspection photo 3, 27 September 2017
  • Ghalia construction site, inspection photo 4, 27 September 2017

6 July 2017

64%+9.7 pts

  • Ghalia construction site, inspection photo 1, 6 July 2017
  • Ghalia construction site, inspection photo 2, 6 July 2017
  • Ghalia construction site, inspection photo 3, 6 July 2017
  • Ghalia construction site, inspection photo 4, 6 July 2017

5 April 2017

54%+21 pts

  • Ghalia construction site, inspection photo 1, 5 April 2017
  • Ghalia construction site, inspection photo 2, 5 April 2017
  • Ghalia construction site, inspection photo 3, 5 April 2017
  • Ghalia construction site, inspection photo 4, 5 April 2017

29 November 2016

33%+13 pts

  • Ghalia construction site, inspection photo 1, 29 November 2016
  • Ghalia construction site, inspection photo 2, 29 November 2016
  • Ghalia construction site, inspection photo 3, 29 November 2016
  • Ghalia construction site, inspection photo 4, 29 November 2016

12 July 2016

20%+8.0 pts

  • Ghalia construction site, inspection photo 1, 12 July 2016
  • Ghalia construction site, inspection photo 2, 12 July 2016
  • Ghalia construction site, inspection photo 3, 12 July 2016
  • Ghalia construction site, inspection photo 4, 12 July 2016

7 January 2016

12%+1.6 pts

  • Ghalia construction site, inspection photo 1, 7 January 2016
  • Ghalia construction site, inspection photo 2, 7 January 2016
  • Ghalia construction site, inspection photo 3, 7 January 2016

All 101 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Ghalia?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Ghalia handover date?
Construction of Ghalia is recorded as complete, with a registered completion date of March 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Ghalia?
Ghalia was 100% built at the site inspection on 28 March 2019. The site has been inspected 13 times since November 2014. The Land Department took 101 site photos at its inspections.
Is Ghalia delayed?
The register lists construction as complete.
Who is building Ghalia?
The registered developer is Damac Development.
Which bank holds the escrow account for Ghalia?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.