Erantis construction progress

The register lists Erantis in Jumeirah Village Circle as complete, with a registered completion date of March 2013. Its last site inspection on record was in June 2013. The developer is Crown One Holding Limited.

100%

Built, at the site inspection of 19 June 2013

Construction complete

Registered completion date
March 2013
Construction started
January 2009
First registered
November 2008
Developer
Crown One Holding Limited
Units
16
Escrow bank
Mashreq Bank
Name in Arabic
ارانتيس
Project number
344
Site inspections
3

Schedule

The register lists Erantis as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2010201120122013
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 June 2013

92%+19 pts

  • Erantis construction site, inspection photo 1, 19 June 2013
  • Erantis construction site, inspection photo 2, 19 June 2013
  • Erantis construction site, inspection photo 3, 19 June 2013
  • Erantis construction site, inspection photo 4, 19 June 2013

13 November 2012

74%

  • Erantis construction site, inspection photo 1, 13 November 2012
  • Erantis construction site, inspection photo 2, 13 November 2012
  • Erantis construction site, inspection photo 3, 13 November 2012
  • Erantis construction site, inspection photo 4, 13 November 2012

10 July 2012

79%

  • Erantis construction site, inspection photo 1, 10 July 2012
  • Erantis construction site, inspection photo 2, 10 July 2012
  • Erantis construction site, inspection photo 3, 10 July 2012
  • Erantis construction site, inspection photo 4, 10 July 2012

All 30 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Erantis?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Erantis handover date?
Construction of Erantis is recorded as complete, with a registered completion date of March 2013. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Erantis?
Erantis was 100% built at the site inspection on 19 June 2013. The site has been inspected 3 times since July 2012. The Land Department took 30 site photos at its inspections.
Is Erantis delayed?
The register lists construction as complete.
Who is building Erantis?
The registered developer is Crown One Holding Limited.
Which bank holds the escrow account for Erantis?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.