City Apartments construction progress
The register lists City Apartments in Jumeirah Village Circle as complete, with a registered completion date of June 2018. Its last site inspection on record was in June 2018. The developer is Virtue Land Real Estate Development.
100%
Built, at the site inspection of 24 June 2018
Construction complete
- Registered completion date
- June 2018
- Construction started
- May 2015
- First registered
- September 2015
- Developer
- Virtue Land Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 70
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- شقق المدينة
- Project number
- 1682
- Site inspections
- 8
Schedule
The register lists City Apartments as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
24 June 2018
100%+8.8 pts
13 February 2018
91%+11 pts
10 October 2017
80%+15 pts
5 June 2017
65%+18 pts
23 February 2017
48%+15 pts
1 November 2016
32%+12 pts
1 June 2016
20%+8.0 pts
12 January 2016
12%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in City Apartments?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the City Apartments handover date?
- Construction of City Apartments is recorded as complete, with a registered completion date of June 2018. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on City Apartments?
- City Apartments was 100% built at the site inspection on 24 June 2018. The site has been inspected 8 times since January 2016. The Land Department took 73 site photos at its inspections.
- Is City Apartments delayed?
- The register lists construction as complete.
- Who is building City Apartments?
- The registered developer is Virtue Land Real Estate Development.
- Which bank holds the escrow account for City Apartments?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.