Chaimaa Avenue construction progress

The register lists Chaimaa Avenue in Jumeirah Village Circle as complete, with a registered completion date of June 2020. Its last site inspection on record was in November 2020. The developer is Deval Real Estate Development.

100%

Built, at the site inspection of 3 November 2020

Construction complete

Registered completion date
June 2020
Construction started
February 2019
First registered
December 2019
Developer
Deval Real Estate Development
Units
89
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
شيماء افنيو
Project number
2183
Site inspections
4

Schedule

The register lists Chaimaa Avenue as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 November 2020

100%+22 pts

  • Chaimaa Avenue construction site, inspection photo 1, 3 November 2020
  • Chaimaa Avenue construction site, inspection photo 2, 3 November 2020
  • Chaimaa Avenue construction site, inspection photo 3, 3 November 2020
  • Chaimaa Avenue construction site, inspection photo 4, 3 November 2020

16 July 2020

78%+27 pts

  • Chaimaa Avenue construction site, inspection photo 1, 16 July 2020
  • Chaimaa Avenue construction site, inspection photo 2, 16 July 2020
  • Chaimaa Avenue construction site, inspection photo 3, 16 July 2020
  • Chaimaa Avenue construction site, inspection photo 4, 16 July 2020

5 February 2020

51%+23 pts

  • Chaimaa Avenue construction site, inspection photo 1, 5 February 2020
  • Chaimaa Avenue construction site, inspection photo 2, 5 February 2020
  • Chaimaa Avenue construction site, inspection photo 3, 5 February 2020
  • Chaimaa Avenue construction site, inspection photo 4, 5 February 2020

22 September 2019

28%

  • Chaimaa Avenue construction site, inspection photo 1, 22 September 2019
  • Chaimaa Avenue construction site, inspection photo 2, 22 September 2019
  • Chaimaa Avenue construction site, inspection photo 3, 22 September 2019
  • Chaimaa Avenue construction site, inspection photo 4, 22 September 2019

All 45 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Deval Real Estate Development has 1 project under construction in Dubai, none past their registered completion dates.

Own a unit in Chaimaa Avenue?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Chaimaa Avenue handover date?
Construction of Chaimaa Avenue is recorded as complete, with a registered completion date of June 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Chaimaa Avenue?
Chaimaa Avenue was 100% built at the site inspection on 3 November 2020. The site has been inspected 4 times since September 2019. The Land Department took 45 site photos at its inspections.
Is Chaimaa Avenue delayed?
The register lists construction as complete.
Who is building Chaimaa Avenue?
The registered developer is Deval Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Chaimaa Avenue?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.