Celestara Residences construction progress
The registered completion date for Celestara Residences in Jumeirah Village Circle is May 2028. At the last site inspection, in November 2026, it was 6.2% built. The developer is Aldhana Real Estate Development.
6.2%
Built, at the site inspection of 5 November 2026
Running behind its date
- Registered completion date
- May 2028
- Finish at recent pace
- July 2045
- Construction started
- May 2025
- First registered
- June 2025
- Developer
- Aldhana Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 121
- Escrow bank
- Al Maryah Community Bank
- Name in Arabic
- سيليستارا ريزيدنسز
- Project number
- 3572
- Site inspections
- 3
Schedule
Between March 2026 and November 2026 the site added about 0.4 points a month. At that rate it would finish around July 2045, more than three months after its registered date of May 2028.
Site inspections
5 November 2026
6.2%+3.1 pts
26 March 2026
3.1%+3.1 pts
16 April 2025
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Celestara Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Celestara Residences handover date?
- The registered completion date is May 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2045. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Celestara Residences?
- Celestara Residences was 6.2% built at the site inspection on 5 November 2026. The site has been inspected 3 times since April 2025. The Land Department took 11 site photos at its inspections.
- Is Celestara Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
- Who is building Celestara Residences?
- The registered developer is Aldhana Real Estate Development.
- Which bank holds the escrow account for Celestara Residences?
- Al Maryah Community Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)