Celestara Residences construction progress

Celestara Residences in Jumeirah Village Circle is 3.1% built at the Land Department inspection of March 2026. Developer Aldhana Real Estate Development. Completion registered for May 2028.

3.1%

Built, at the Land Department site inspection of 26 March 2026

Running behind its date

Completion date (Land Department)
May 2028
Finish at recent pace
April 2055
Construction started
May 2025
Registered with the Land Department
June 2025
Developer
Aldhana Real Estate Development
Units
121
Escrow bank
Al Maryah Community Bank
Name in Arabic
سيليستارا ريزيدنسز
Land Department project number
3572
Land Department site inspections
2

Schedule

Between April 2025 and March 2026 the site added about 0.3 points a month. At that rate it would finish around April 2055, more than three months after the May 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

26 March 2026

3.1%+3.1 pts

  • Celestara Residences construction site, Land Department inspection photo 1, 26 March 2026
  • Celestara Residences construction site, Land Department inspection photo 2, 26 March 2026
  • Celestara Residences construction site, Land Department inspection photo 3, 26 March 2026

16 April 2025

0%

  • Celestara Residences construction site, Land Department inspection photo 1, 16 April 2025
  • Celestara Residences construction site, Land Department inspection photo 2, 16 April 2025
  • Celestara Residences construction site, Land Department inspection photo 3, 16 April 2025

All 6 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Own a unit in Celestara Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Celestara Residences be completed?
The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around April 2055. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Celestara Residences is built?
3.1%, measured at the Land Department site inspection on 26 March 2026. The Land Department engineers have inspected the site 2 times since April 2025.
Is Celestara Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building Celestara Residences?
The registered developer is Aldhana Real Estate Development.
Which bank holds the escrow account for Celestara Residences?
Al Maryah Community Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.