Capital One construction progress

The registered completion date for Capital One in Jumeirah Village Circle is July 2028. At the last site inspection, in November 2026, it was 6.9% built. The developer is Centurion Star Developers.

6.9%

Built, at the site inspection of 5 November 2026

Running behind its date

Registered completion date
July 2028
Finish at recent pace
May 2039
Construction started
July 2025
First registered
June 2025
Developer
Centurion Star Developers
Units
128
Escrow bank
Emirates Islamic Bank
Name in Arabic
Capital One
Project number
3789
Site inspections
4

Schedule

Between April 2026 and November 2026 the site added about 0.6 points a month. At that rate it would finish around May 2039, more than three months after its registered date of July 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 November 2026

6.9%+0.7 pts

  • Capital One construction site, inspection photo 1, 5 November 2026
  • Capital One construction site, inspection photo 2, 5 November 2026

27 July 2026

6.2%+3.5 pts

  • Capital One construction site, inspection photo 1, 27 July 2026
  • Capital One construction site, inspection photo 2, 27 July 2026
  • Capital One construction site, inspection photo 3, 27 July 2026
  • Capital One construction site, inspection photo 4, 27 July 2026

13 April 2026

2.7%+2.7 pts

  • Capital One construction site, inspection photo 1, 13 April 2026
  • Capital One construction site, inspection photo 2, 13 April 2026

3 June 2025

0%

  • Capital One construction site, inspection photo 1, 3 June 2025
  • Capital One construction site, inspection photo 2, 3 June 2025

All 10 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Capital One?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Capital One handover date?
The registered completion date is July 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2039. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Capital One?
Capital One was 6.9% built at the site inspection on 5 November 2026. The site has been inspected 4 times since June 2025. The Land Department took 10 site photos at its inspections.
Is Capital One delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2028.
Who is building Capital One?
The registered developer is Centurion Star Developers.
Which bank holds the escrow account for Capital One?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.