Capital One construction progress

Capital One in Jumeirah Village Circle is 6.2% built at the Land Department inspection of July 2026. Developer Centurion Star Developers. Completion registered for July 2028.

6.2%

Built, at the Land Department site inspection of 27 July 2026

Running behind its date

Completion date (Land Department)
July 2028
Finish at recent pace
April 2034
Construction started
July 2025
Registered with the Land Department
June 2025
Developer
Centurion Star Developers
Units
128
Escrow bank
Banque Misr
Name in Arabic
Capital One
Land Department project number
3789
Land Department site inspections
3

Schedule

Between April 2026 and July 2026 the site added about 1.0 points a month. At that rate it would finish around April 2034, more than three months after the July 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

27 July 2026

6.2%+3.5 pts

  • Capital One construction site, Land Department inspection photo 1, 27 July 2026
  • Capital One construction site, Land Department inspection photo 2, 27 July 2026
  • Capital One construction site, Land Department inspection photo 3, 27 July 2026
  • Capital One construction site, Land Department inspection photo 4, 27 July 2026

13 April 2026

2.7%+2.7 pts

  • Capital One construction site, Land Department inspection photo 1, 13 April 2026
  • Capital One construction site, Land Department inspection photo 2, 13 April 2026

3 June 2025

0%

  • Capital One construction site, Land Department inspection photo 1, 3 June 2025
  • Capital One construction site, Land Department inspection photo 2, 3 June 2025

All 8 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Own a unit in Capital One?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Capital One be completed?
The completion date registered with the Dubai Land Department is July 2028. At the pace of its recent inspections the site would reach 100% around April 2034. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Capital One is built?
6.2%, measured at the Land Department site inspection on 27 July 2026. The Land Department engineers have inspected the site 3 times since June 2025.
Is Capital One delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2028.
Who is building Capital One?
The registered developer is Centurion Star Developers.
Which bank holds the escrow account for Capital One?
Banque Misr. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.