Capital One construction progress
The registered completion date for Capital One in Jumeirah Village Circle is July 2028. At the last site inspection, in November 2026, it was 6.9% built. The developer is Centurion Star Developers.
6.9%
Built, at the site inspection of 5 November 2026
Running behind its date
- Registered completion date
- July 2028
- Finish at recent pace
- May 2039
- Construction started
- July 2025
- First registered
- June 2025
- Developer
- Centurion Star Developers
- Community
- Jumeirah Village Circle
- Units
- 128
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- Capital One
- Project number
- 3789
- Site inspections
- 4
Schedule
Between April 2026 and November 2026 the site added about 0.6 points a month. At that rate it would finish around May 2039, more than three months after its registered date of July 2028.
Site inspections
5 November 2026
6.9%+0.7 pts
27 July 2026
6.2%+3.5 pts
13 April 2026
2.7%+2.7 pts
3 June 2025
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Capital One?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Capital One handover date?
- The registered completion date is July 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2039. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Capital One?
- Capital One was 6.9% built at the site inspection on 5 November 2026. The site has been inspected 4 times since June 2025. The Land Department took 10 site photos at its inspections.
- Is Capital One delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2028.
- Who is building Capital One?
- The registered developer is Centurion Star Developers.
- Which bank holds the escrow account for Capital One?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.