Avant Garde Residences II By Skyline construction progress

The registered completion date for Avant Garde Residences II By Skyline in Jumeirah Village Circle is September 2028. At the last site inspection, in November 2026, it was 8.9% built. The developer is Skyline Builders Real Estate.

8.9%

Built, at the site inspection of 5 November 2026

Running behind its date

Registered completion date
September 2028
Finish at recent pace
September 2035
Construction started
October 2025
First registered
July 2025
Developer
Skyline Builders Real Estate
Units
223
Escrow bank
First Abu Dhabi Bank
Name in Arabic
اوانت جارد رسيدانس Ii من سكاي لاين بلدرز للعقارات
Project number
3792
Site inspections
5

Schedule

Between December 2025 and November 2026 the site added about 0.9 points a month. At that rate it would finish around September 2035, more than three months after its registered date of September 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 November 2026

8.9%+1.6 pts

  • Avant Garde Residences II By Skyline construction site, inspection photo 1, 5 November 2026
  • Avant Garde Residences II By Skyline construction site, inspection photo 2, 5 November 2026
  • Avant Garde Residences II By Skyline construction site, inspection photo 3, 5 November 2026
  • Avant Garde Residences II By Skyline construction site, inspection photo 4, 5 November 2026

30 July 2026

7.3%+3.3 pts

  • Avant Garde Residences II By Skyline construction site, inspection photo 1, 30 July 2026
  • Avant Garde Residences II By Skyline construction site, inspection photo 2, 30 July 2026
  • Avant Garde Residences II By Skyline construction site, inspection photo 3, 30 July 2026

22 April 2026

4.0%+3.8 pts

  • Avant Garde Residences II By Skyline construction site, inspection photo 1, 22 April 2026
  • Avant Garde Residences II By Skyline construction site, inspection photo 2, 22 April 2026
  • Avant Garde Residences II By Skyline construction site, inspection photo 3, 22 April 2026

30 December 2025

0.2%+0.2 pts

  • Avant Garde Residences II By Skyline construction site, inspection photo 1, 30 December 2025
  • Avant Garde Residences II By Skyline construction site, inspection photo 2, 30 December 2025
  • Avant Garde Residences II By Skyline construction site, inspection photo 3, 30 December 2025
  • Avant Garde Residences II By Skyline construction site, inspection photo 4, 30 December 2025

27 May 2025

0%

  • Avant Garde Residences II By Skyline construction site, inspection photo 1, 27 May 2025
  • Avant Garde Residences II By Skyline construction site, inspection photo 2, 27 May 2025

All 17 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Avant Garde Residences II By Skyline?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Avant Garde Residences II By Skyline handover date?
The registered completion date is September 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2035. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Avant Garde Residences II By Skyline?
Avant Garde Residences II By Skyline was 8.9% built at the site inspection on 5 November 2026. The site has been inspected 5 times since May 2025. The Land Department took 17 site photos at its inspections.
Is Avant Garde Residences II By Skyline delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building Avant Garde Residences II By Skyline?
The registered developer is Skyline Builders Real Estate.
Which bank holds the escrow account for Avant Garde Residences II By Skyline?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.