Avana Residences By Deca Real Estate Development construction progress

The registered completion date for Avana Residences By Deca Real Estate Development in Jumeirah Village Circle is November 2027. At the last site inspection, in April 2026, it was 3.0% built. The developer is Deca Real Estate Development.

3.1%

Built, at the site inspection of 21 April 2026

Running behind its date

Registered completion date
November 2027
Finish at recent pace
December 2054
Construction started
May 2025
First registered
August 2025
Developer
Deca Real Estate Development
Units
167
Escrow bank
Ajman Bank
Name in Arabic
افانا ريزيدنسز من ديكا للتطوير العقاري
Project number
3790
Site inspections
2

Schedule

Between June 2025 and April 2026 the site added about 0.3 points a month. At that rate it would finish around December 2054, more than three months after its registered date of November 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 April 2026

3.0%+3.0 pts

  • Avana Residences By Deca Real Estate Development construction site, inspection photo 1, 21 April 2026
  • Avana Residences By Deca Real Estate Development construction site, inspection photo 2, 21 April 2026

1 June 2025

0%

  • Avana Residences By Deca Real Estate Development construction site, inspection photo 1, 1 June 2025
  • Avana Residences By Deca Real Estate Development construction site, inspection photo 2, 1 June 2025

All 4 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Avana Residences By Deca Real Estate Development?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Avana Residences By Deca Real Estate Development handover date?
The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2054. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Avana Residences By Deca Real Estate Development?
Avana Residences By Deca Real Estate Development was 3.1% built at the site inspection on 21 April 2026. The site has been inspected 2 times since June 2025. The Land Department took 4 site photos at its inspections.
Is Avana Residences By Deca Real Estate Development delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Avana Residences By Deca Real Estate Development?
The registered developer is Deca Real Estate Development.
Which bank holds the escrow account for Avana Residences By Deca Real Estate Development?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.