Ashton Park Residences The Second construction progress

Ashton Park Residences The Second in Jumeirah Village Circle is 70% built at the Land Department inspection of June 2026. Developer Ashton Real Estate Development. Completion registered for December 2025.

70%

Built, at the Land Department site inspection of 1 June 2026

9 months past its registered completion date

Completion date (Land Department)
December 2025
Finish at recent pace
November 2026
Construction started
November 2024
Registered with the Land Department
September 2024
Developer
Ashton Real Estate Development
Units
194
Escrow bank
Sharjah Islamic Bank
Name in Arabic
أشتون بارك ريزيدنسز الثاني
Land Department project number
3263
Land Department site inspections
5

Schedule

Ashton Park Residences The Second was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 5.1 points a month. Kept at that rate, the site would reach 100% around November 2026.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

1 June 2026

70%+14 pts

  • Ashton Park Residences The Second construction site, Land Department inspection photo 1, 1 June 2026
  • Ashton Park Residences The Second construction site, Land Department inspection photo 2, 1 June 2026
  • Ashton Park Residences The Second construction site, Land Department inspection photo 3, 1 June 2026
  • Ashton Park Residences The Second construction site, Land Department inspection photo 4, 1 June 2026

17 February 2026

56%+31 pts

  • Ashton Park Residences The Second construction site, Land Department inspection photo 1, 17 February 2026
  • Ashton Park Residences The Second construction site, Land Department inspection photo 2, 17 February 2026
  • Ashton Park Residences The Second construction site, Land Department inspection photo 3, 17 February 2026
  • Ashton Park Residences The Second construction site, Land Department inspection photo 4, 17 February 2026

23 October 2025

26%+12 pts

  • Ashton Park Residences The Second construction site, Land Department inspection photo 1, 23 October 2025
  • Ashton Park Residences The Second construction site, Land Department inspection photo 2, 23 October 2025
  • Ashton Park Residences The Second construction site, Land Department inspection photo 3, 23 October 2025
  • Ashton Park Residences The Second construction site, Land Department inspection photo 4, 23 October 2025

2 July 2025

14%+14 pts

  • Ashton Park Residences The Second construction site, Land Department inspection photo 1, 2 July 2025
  • Ashton Park Residences The Second construction site, Land Department inspection photo 2, 2 July 2025
  • Ashton Park Residences The Second construction site, Land Department inspection photo 3, 2 July 2025
  • Ashton Park Residences The Second construction site, Land Department inspection photo 4, 2 July 2025

30 August 2024

0%

  • Ashton Park Residences The Second construction site, Land Department inspection photo 1, 30 August 2024
  • Ashton Park Residences The Second construction site, Land Department inspection photo 2, 30 August 2024

All 38 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Own a unit in Ashton Park Residences The Second?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Ashton Park Residences The Second be completed?
The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around November 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Ashton Park Residences The Second is built?
70%, measured at the Land Department site inspection on 1 June 2026. The Land Department engineers have inspected the site 5 times since August 2024.
Is Ashton Park Residences The Second delayed?
Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
Who is building Ashton Park Residences The Second?
The registered developer is Ashton Real Estate Development.
Which bank holds the escrow account for Ashton Park Residences The Second?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.