Ashton Park Residences The Second construction progress
Ashton Park Residences The Second in Jumeirah Village Circle is 70% built at the Land Department inspection of June 2026. Developer Ashton Real Estate Development. Completion registered for December 2025.
70%
Built, at the Land Department site inspection of 1 June 2026
9 months past its registered completion date
- Completion date (Land Department)
- December 2025
- Finish at recent pace
- November 2026
- Construction started
- November 2024
- Registered with the Land Department
- September 2024
- Developer
- Ashton Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 194
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- أشتون بارك ريزيدنسز الثاني
- Land Department project number
- 3263
- Land Department site inspections
- 5
Schedule
Ashton Park Residences The Second was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 5.1 points a month. Kept at that rate, the site would reach 100% around November 2026.
Site inspections
1 June 2026
70%+14 pts
17 February 2026
56%+31 pts
23 October 2025
26%+12 pts
2 July 2025
14%+14 pts
30 August 2024
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Own a unit in Ashton Park Residences The Second?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Ashton Park Residences The Second be completed?
- The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around November 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Ashton Park Residences The Second is built?
- 70%, measured at the Land Department site inspection on 1 June 2026. The Land Department engineers have inspected the site 5 times since August 2024.
- Is Ashton Park Residences The Second delayed?
- Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
- Who is building Ashton Park Residences The Second?
- The registered developer is Ashton Real Estate Development.
- Which bank holds the escrow account for Ashton Park Residences The Second?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)