Ashton Park Residences The Second construction progress

Ashton Park Residences The Second in Jumeirah Village Circle was registered to complete in December 2025 and is still under construction. At the last site inspection, in November 2026, it was 93% built. The developer is Ashton Real Estate Development.

93%

Built, at the site inspection of 23 November 2026

11 months past its registered completion date

Registered completion date
December 2025
Finish at recent pace
January 2027
Construction started
November 2024
First registered
September 2024
Developer
Ashton Real Estate Development
Units
194
Escrow bank
Sharjah Islamic Bank
Name in Arabic
أشتون بارك ريزيدنسز الثاني
Project number
3263
Site inspections
6

Schedule

Ashton Park Residences The Second was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 4.0 points a month. Kept at that rate, the site would reach 100% around January 2027.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 November 2026

93%+23 pts

  • Ashton Park Residences The Second construction site, inspection photo 1, 23 November 2026
  • Ashton Park Residences The Second construction site, inspection photo 2, 23 November 2026
  • Ashton Park Residences The Second construction site, inspection photo 3, 23 November 2026
  • Ashton Park Residences The Second construction site, inspection photo 4, 23 November 2026

1 June 2026

70%+14 pts

  • Ashton Park Residences The Second construction site, inspection photo 1, 1 June 2026
  • Ashton Park Residences The Second construction site, inspection photo 2, 1 June 2026
  • Ashton Park Residences The Second construction site, inspection photo 3, 1 June 2026
  • Ashton Park Residences The Second construction site, inspection photo 4, 1 June 2026

17 February 2026

56%+31 pts

  • Ashton Park Residences The Second construction site, inspection photo 1, 17 February 2026
  • Ashton Park Residences The Second construction site, inspection photo 2, 17 February 2026
  • Ashton Park Residences The Second construction site, inspection photo 3, 17 February 2026
  • Ashton Park Residences The Second construction site, inspection photo 4, 17 February 2026

23 October 2025

26%+12 pts

  • Ashton Park Residences The Second construction site, inspection photo 1, 23 October 2025
  • Ashton Park Residences The Second construction site, inspection photo 2, 23 October 2025
  • Ashton Park Residences The Second construction site, inspection photo 3, 23 October 2025
  • Ashton Park Residences The Second construction site, inspection photo 4, 23 October 2025

2 July 2025

14%+14 pts

  • Ashton Park Residences The Second construction site, inspection photo 1, 2 July 2025
  • Ashton Park Residences The Second construction site, inspection photo 2, 2 July 2025
  • Ashton Park Residences The Second construction site, inspection photo 3, 2 July 2025
  • Ashton Park Residences The Second construction site, inspection photo 4, 2 July 2025

30 August 2024

0%

  • Ashton Park Residences The Second construction site, inspection photo 1, 30 August 2024
  • Ashton Park Residences The Second construction site, inspection photo 2, 30 August 2024

All 48 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Ashton Park Residences The Second?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ashton Park Residences The Second handover date?
The registered completion date was December 2025, and the register still lists Ashton Park Residences The Second as under construction. At the pace of its recent inspections the site would reach 100% around January 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Ashton Park Residences The Second?
Ashton Park Residences The Second was 93% built at the site inspection on 23 November 2026. The site has been inspected 6 times since August 2024. The Land Department took 48 site photos at its inspections.
Is Ashton Park Residences The Second delayed?
Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
Who is building Ashton Park Residences The Second?
The registered developer is Ashton Real Estate Development.
Which bank holds the escrow account for Ashton Park Residences The Second?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.