Aria construction progress

The register lists Aria in Jumeirah Village Circle as complete, with a registered completion date of March 2021. Its last site inspection on record was in March 2021. The developer is Grovy Real Estate Development.

100%

Built, at the site inspection of 10 March 2021

Construction complete

Registered completion date
March 2021
Construction started
January 2019
First registered
November 2019
Developer
Grovy Real Estate Development
Units
125
Escrow bank
Bank of Baroda
Name in Arabic
آريا
Project number
2179
Site inspections
5

Schedule

The register lists Aria as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 March 2021

100%+9.9 pts

  • Aria construction site, inspection photo 1, 10 March 2021
  • Aria construction site, inspection photo 2, 10 March 2021
  • Aria construction site, inspection photo 3, 10 March 2021
  • Aria construction site, inspection photo 4, 10 March 2021

20 October 2020

90%+30 pts

  • Aria construction site, inspection photo 1, 20 October 2020
  • Aria construction site, inspection photo 2, 20 October 2020
  • Aria construction site, inspection photo 3, 20 October 2020
  • Aria construction site, inspection photo 4, 20 October 2020

16 June 2020

60%+17 pts

  • Aria construction site, inspection photo 1, 16 June 2020
  • Aria construction site, inspection photo 2, 16 June 2020
  • Aria construction site, inspection photo 3, 16 June 2020
  • Aria construction site, inspection photo 4, 16 June 2020

3 February 2020

43%+21 pts

  • Aria construction site, inspection photo 1, 3 February 2020
  • Aria construction site, inspection photo 2, 3 February 2020
  • Aria construction site, inspection photo 3, 3 February 2020
  • Aria construction site, inspection photo 4, 3 February 2020

15 September 2019

22%

  • Aria construction site, inspection photo 1, 15 September 2019
  • Aria construction site, inspection photo 2, 15 September 2019
  • Aria construction site, inspection photo 3, 15 September 2019
  • Aria construction site, inspection photo 4, 15 September 2019

All 60 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Aria?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Aria handover date?
Construction of Aria is recorded as complete, with a registered completion date of March 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Aria?
Aria was 100% built at the site inspection on 10 March 2021. The site has been inspected 5 times since September 2019. The Land Department took 60 site photos at its inspections.
Is Aria delayed?
The register lists construction as complete.
Who is building Aria?
The registered developer is Grovy Real Estate Development.
Which bank holds the escrow account for Aria?
Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.