Almaan 101 construction progress

Almaan 101 in Jumeirah Village Circle was registered to complete in April 2026 and is still under construction. At the last site inspection, in July 2026, it was 51% built. The developer is M N Vision Real Estate Development.

51%

Built, at the site inspection of 10 July 2026

8 months past its registered completion date

Registered completion date
April 2026
Finish at recent pace
May 2028
Construction started
October 2024
First registered
January 2025
Developer
M N Vision Real Estate Development
Units
102
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
المان 101
Project number
3402
Site inspections
4

Schedule

Almaan 101 was registered to complete in April 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 2.2 points a month. Kept at that rate, the site would reach 100% around May 2028.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 July 2026

51%+11 pts

  • Almaan 101 construction site, inspection photo 1, 10 July 2026
  • Almaan 101 construction site, inspection photo 2, 10 July 2026
  • Almaan 101 construction site, inspection photo 3, 10 July 2026
  • Almaan 101 construction site, inspection photo 4, 10 July 2026

4 December 2025

40%+14 pts

  • Almaan 101 construction site, inspection photo 1, 4 December 2025
  • Almaan 101 construction site, inspection photo 2, 4 December 2025
  • Almaan 101 construction site, inspection photo 3, 4 December 2025
  • Almaan 101 construction site, inspection photo 4, 4 December 2025

28 July 2025

26%+26 pts

  • Almaan 101 construction site, inspection photo 1, 28 July 2025
  • Almaan 101 construction site, inspection photo 2, 28 July 2025
  • Almaan 101 construction site, inspection photo 3, 28 July 2025
  • Almaan 101 construction site, inspection photo 4, 28 July 2025

27 November 2024

0%

  • Almaan 101 construction site, inspection photo 1, 27 November 2024
  • Almaan 101 construction site, inspection photo 2, 27 November 2024

All 24 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Almaan 101?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Almaan 101 handover date?
The registered completion date was April 2026, and the register still lists Almaan 101 as under construction. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Almaan 101?
Almaan 101 was 51% built at the site inspection on 10 July 2026. The site has been inspected 4 times since November 2024. The Land Department took 24 site photos at its inspections.
Is Almaan 101 delayed?
Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
Who is building Almaan 101?
The registered developer is M N Vision Real Estate Development.
Which bank holds the escrow account for Almaan 101?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.