Almaan 101 construction progress
Almaan 101 in Jumeirah Village Circle is 51% built at the Land Department inspection of July 2026. Developer M N Vision Real Estate Development. Completion registered for April 2026.
51%
Built, at the Land Department site inspection of 10 July 2026
6 months past its registered completion date
- Completion date (Land Department)
- April 2026
- Finish at recent pace
- May 2028
- Construction started
- October 2024
- Registered with the Land Department
- January 2025
- Developer
- M N Vision Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 102
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- المان 101
- Land Department project number
- 3402
- Land Department site inspections
- 4
Schedule
Almaan 101 was registered to complete in April 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 2.2 points a month. Kept at that rate, the site would reach 100% around May 2028.
Site inspections
10 July 2026
51%+11 pts
4 December 2025
40%+14 pts
28 July 2025
26%+26 pts
27 November 2024
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Own a unit in Almaan 101?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Almaan 101 be completed?
- The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around May 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Almaan 101 is built?
- 51%, measured at the Land Department site inspection on 10 July 2026. The Land Department engineers have inspected the site 4 times since November 2024.
- Is Almaan 101 delayed?
- Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
- Who is building Almaan 101?
- The registered developer is M N Vision Real Estate Development.
- Which bank holds the escrow account for Almaan 101?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.