Alfal Residences construction progress

The registered completion date for Alfal Residences in Jumeirah Village Circle is February 2027. At the last site inspection, in September 2026, it was 25% built. The developer is Dubuild Real Estate Development.

25%

Built, at the site inspection of 25 September 2026

Running behind its date

Registered completion date
February 2027
Finish at recent pace
September 2030
Construction started
July 2024
First registered
August 2024
Developer
Dubuild Real Estate Development
Units
285
Escrow bank
Emirates Islamic Bank
Name in Arabic
الفال ريزيدنسيز
Project number
3190
Site inspections
5

Schedule

Between November 2025 and September 2026 the site added about 1.6 points a month. At that rate it would finish around September 2030, more than three months after its registered date of February 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 September 2026

25%+11 pts

  • Alfal Residences construction site, inspection photo 1, 25 September 2026
  • Alfal Residences construction site, inspection photo 2, 25 September 2026
  • Alfal Residences construction site, inspection photo 3, 25 September 2026
  • Alfal Residences construction site, inspection photo 4, 25 September 2026

4 March 2026

14%+4.4 pts

  • Alfal Residences construction site, inspection photo 1, 4 March 2026
  • Alfal Residences construction site, inspection photo 2, 4 March 2026
  • Alfal Residences construction site, inspection photo 3, 4 March 2026
  • Alfal Residences construction site, inspection photo 4, 4 March 2026

26 November 2025

9.3%+1.5 pts

  • Alfal Residences construction site, inspection photo 1, 26 November 2025
  • Alfal Residences construction site, inspection photo 2, 26 November 2025
  • Alfal Residences construction site, inspection photo 3, 26 November 2025
  • Alfal Residences construction site, inspection photo 4, 26 November 2025

9 July 2025

7.7%+7.7 pts

  • Alfal Residences construction site, inspection photo 1, 9 July 2025
  • Alfal Residences construction site, inspection photo 2, 9 July 2025
  • Alfal Residences construction site, inspection photo 3, 9 July 2025
  • Alfal Residences construction site, inspection photo 4, 9 July 2025

6 August 2024

0%

  • Alfal Residences construction site, inspection photo 1, 6 August 2024
  • Alfal Residences construction site, inspection photo 2, 6 August 2024
  • Alfal Residences construction site, inspection photo 3, 6 August 2024

All 29 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Alfal Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Alfal Residences handover date?
The registered completion date is February 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Alfal Residences?
Alfal Residences was 25% built at the site inspection on 25 September 2026. The site has been inspected 5 times since August 2024. The Land Department took 29 site photos at its inspections.
Is Alfal Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
Who is building Alfal Residences?
The registered developer is Dubuild Real Estate Development.
Which bank holds the escrow account for Alfal Residences?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.