Skip to content

7 West Villas construction progress

The register lists 7 West Villas in Jumeirah Village Circle as complete, with a registered completion date of December 2015. Its last site inspection on record was in March 2016. The developer is A. S. A 1 Developers Limited.

100%

Built, at the site inspection of 1 March 2016

Construction complete

Registered completion date
December 2015
Construction started
August 2009
First registered
November 2008
Developer
A. S. A 1 Developers Limited
Units
14
Escrow bank
Dubai Islamic Bank
Name in Arabic
7 ويست فيلا
Project number
353
Site inspections
4

Schedule

The register lists 7 West Villas as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2010201220142016
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 March 2016

100%+20 pts

  • 7 West Villas construction site, inspection photo 1, 1 March 2016
  • 7 West Villas construction site, inspection photo 2, 1 March 2016
  • 7 West Villas construction site, inspection photo 3, 1 March 2016
  • 7 West Villas construction site, inspection photo 4, 1 March 2016

24 August 2014

80%+1.0 pts

  • 7 West Villas construction site, inspection photo 1, 24 August 2014
  • 7 West Villas construction site, inspection photo 2, 24 August 2014
  • 7 West Villas construction site, inspection photo 3, 24 August 2014
  • 7 West Villas construction site, inspection photo 4, 24 August 2014

14 April 2014

79%

  • 7 West Villas construction site, inspection photo 1, 14 April 2014
  • 7 West Villas construction site, inspection photo 2, 14 April 2014
  • 7 West Villas construction site, inspection photo 3, 14 April 2014
  • 7 West Villas construction site, inspection photo 4, 14 April 2014

16 October 2012

84%

  • 7 West Villas construction site, inspection photo 1, 16 October 2012
  • 7 West Villas construction site, inspection photo 2, 16 October 2012
  • 7 West Villas construction site, inspection photo 3, 16 October 2012
  • 7 West Villas construction site, inspection photo 4, 16 October 2012

All 41 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in 7 West Villas?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the 7 West Villas handover date?
Construction of 7 West Villas is recorded as complete, with a registered completion date of December 2015. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on 7 West Villas?
7 West Villas was 100% built at the site inspection on 1 March 2016. The site has been inspected 4 times since October 2012. The Land Department took 41 site photos at its inspections.
Is 7 West Villas delayed?
The register lists construction as complete.
Who is building 7 West Villas?
The registered developer is A. S. A 1 Developers Limited.
Which bank holds the escrow account for 7 West Villas?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.