311 Boulevard By Bam Eskan construction progress
The registered completion date for 311 Boulevard By Bam Eskan in Jumeirah Village Circle is October 2027. At the last site inspection, in August 2026, it was 10% built. The developer is Bam Eskan Real Estate Development.
14%
Built, at the site inspection of 17 August 2026
Running behind its date
- Registered completion date
- October 2027
- Finish at recent pace
- August 2033
- Construction started
- April 2025
- First registered
- February 2025
- Developer
- Bam Eskan Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 399
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- 311 بوليفارد بواسطة بام اسكان
- Project number
- 3320
- Site inspections
- 3
Schedule
Between February 2026 and August 2026 the site added about 1.1 points a month. At that rate it would finish around August 2033, more than three months after its registered date of October 2027.
Site inspections
17 August 2026
10%+6.1 pts
25 February 2026
3.9%+3.9 pts
8 October 2024
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in 311 Boulevard By Bam Eskan?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the 311 Boulevard By Bam Eskan handover date?
- The registered completion date is October 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on 311 Boulevard By Bam Eskan?
- 311 Boulevard By Bam Eskan was 14% built at the site inspection on 17 August 2026. The site has been inspected 3 times since October 2024. The Land Department took 11 site photos at its inspections.
- Is 311 Boulevard By Bam Eskan delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
- Who is building 311 Boulevard By Bam Eskan?
- The registered developer is Bam Eskan Real Estate Development.
- Which bank holds the escrow account for 311 Boulevard By Bam Eskan?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)