Red Wood Park construction progress

The register lists Red Wood Park in Jumeirah Golf Estates as complete, with a registered completion date of November 2016. Its last site inspection on record was in January 2017. The developer is Jumeirah Golf Estates.

100%

Built, at the site inspection of 12 January 2017

Construction complete

Registered completion date
November 2016
Construction started
January 2015
First registered
September 2014
Developer
Jumeirah Golf Estates
Units
35
Escrow bank
Mashreq Bank
Name in Arabic
ريد وود بارك
Project number
1584
Site inspections
5

Schedule

The register lists Red Wood Park as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20162017
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 January 2017

100%+24 pts

  • Red Wood Park construction site, inspection photo 1, 12 January 2017
  • Red Wood Park construction site, inspection photo 2, 12 January 2017
  • Red Wood Park construction site, inspection photo 3, 12 January 2017
  • Red Wood Park construction site, inspection photo 4, 12 January 2017

27 June 2016

76%+14 pts

  • Red Wood Park construction site, inspection photo 1, 27 June 2016
  • Red Wood Park construction site, inspection photo 2, 27 June 2016
  • Red Wood Park construction site, inspection photo 3, 27 June 2016
  • Red Wood Park construction site, inspection photo 4, 27 June 2016

26 April 2016

62%+19 pts

  • Red Wood Park construction site, inspection photo 1, 26 April 2016
  • Red Wood Park construction site, inspection photo 2, 26 April 2016
  • Red Wood Park construction site, inspection photo 3, 26 April 2016
  • Red Wood Park construction site, inspection photo 4, 26 April 2016

23 December 2015

43%+13 pts

  • Red Wood Park construction site, inspection photo 1, 23 December 2015
  • Red Wood Park construction site, inspection photo 2, 23 December 2015
  • Red Wood Park construction site, inspection photo 3, 23 December 2015
  • Red Wood Park construction site, inspection photo 4, 23 December 2015

19 October 2015

30%

  • Red Wood Park construction site, inspection photo 1, 19 October 2015
  • Red Wood Park construction site, inspection photo 2, 19 October 2015
  • Red Wood Park construction site, inspection photo 3, 19 October 2015
  • Red Wood Park construction site, inspection photo 4, 19 October 2015

All 47 site photos, by inspection date

Context

Jumeirah Golf Estates has 4 projects under construction, 49% built on average.

Own a unit in Red Wood Park?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Red Wood Park handover date?
Construction of Red Wood Park is recorded as complete, with a registered completion date of November 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Red Wood Park?
Red Wood Park was 100% built at the site inspection on 12 January 2017. The site has been inspected 5 times since October 2015. The Land Department took 47 site photos at its inspections.
Is Red Wood Park delayed?
The register lists construction as complete.
Who is building Red Wood Park?
The registered developer is Jumeirah Golf Estates.
Which bank holds the escrow account for Red Wood Park?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.