Alandalus Townhouse construction progress

The register lists Alandalus Townhouse in Jumeirah Golf Estates as complete, with a registered completion date of October 2020. Its last site inspection on record was in October 2020. The developer is Jumeirah Golf Estates.

100%

Built, at the site inspection of 5 October 2020

Construction complete

Registered completion date
October 2020
Construction started
August 2017
First registered
February 2017
Developer
Jumeirah Golf Estates
Units
95
Escrow bank
Mashreq Bank
Name in Arabic
الأندلس تاون هاوس
Project number
1856
Site inspections
9

Schedule

The register lists Alandalus Townhouse as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 October 2020

100%+1.5 pts

  • Alandalus Townhouse construction site, inspection photo 1, 5 October 2020
  • Alandalus Townhouse construction site, inspection photo 2, 5 October 2020
  • Alandalus Townhouse construction site, inspection photo 3, 5 October 2020
  • Alandalus Townhouse construction site, inspection photo 4, 5 October 2020

28 May 2020

98%+2.6 pts

  • Alandalus Townhouse construction site, inspection photo 1, 28 May 2020
  • Alandalus Townhouse construction site, inspection photo 2, 28 May 2020
  • Alandalus Townhouse construction site, inspection photo 3, 28 May 2020
  • Alandalus Townhouse construction site, inspection photo 4, 28 May 2020

13 November 2019

96%+1.5 pts

  • Alandalus Townhouse construction site, inspection photo 1, 13 November 2019
  • Alandalus Townhouse construction site, inspection photo 2, 13 November 2019
  • Alandalus Townhouse construction site, inspection photo 3, 13 November 2019
  • Alandalus Townhouse construction site, inspection photo 4, 13 November 2019

6 October 2019

94%+1.3 pts

  • Alandalus Townhouse construction site, inspection photo 1, 6 October 2019
  • Alandalus Townhouse construction site, inspection photo 2, 6 October 2019
  • Alandalus Townhouse construction site, inspection photo 3, 6 October 2019
  • Alandalus Townhouse construction site, inspection photo 4, 6 October 2019

3 September 2019

93%+2.6 pts

  • Alandalus Townhouse construction site, inspection photo 1, 3 September 2019
  • Alandalus Townhouse construction site, inspection photo 2, 3 September 2019
  • Alandalus Townhouse construction site, inspection photo 3, 3 September 2019
  • Alandalus Townhouse construction site, inspection photo 4, 3 September 2019

30 June 2019

90%+60 pts

  • Alandalus Townhouse construction site, inspection photo 1, 30 June 2019
  • Alandalus Townhouse construction site, inspection photo 2, 30 June 2019
  • Alandalus Townhouse construction site, inspection photo 3, 30 June 2019
  • Alandalus Townhouse construction site, inspection photo 4, 30 June 2019

25 March 2018

30%+17 pts

  • Alandalus Townhouse construction site, inspection photo 1, 25 March 2018
  • Alandalus Townhouse construction site, inspection photo 2, 25 March 2018
  • Alandalus Townhouse construction site, inspection photo 3, 25 March 2018
  • Alandalus Townhouse construction site, inspection photo 4, 25 March 2018

25 December 2017

13%+6.4 pts

  • Alandalus Townhouse construction site, inspection photo 1, 25 December 2017
  • Alandalus Townhouse construction site, inspection photo 2, 25 December 2017
  • Alandalus Townhouse construction site, inspection photo 3, 25 December 2017
  • Alandalus Townhouse construction site, inspection photo 4, 25 December 2017

10 September 2017

6.6%

  • Alandalus Townhouse construction site, inspection photo 1, 10 September 2017
  • Alandalus Townhouse construction site, inspection photo 2, 10 September 2017
  • Alandalus Townhouse construction site, inspection photo 3, 10 September 2017
  • Alandalus Townhouse construction site, inspection photo 4, 10 September 2017

All 88 site photos, by inspection date

Context

Jumeirah Golf Estates has 4 projects under construction, 49% built on average.

Own a unit in Alandalus Townhouse?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Alandalus Townhouse handover date?
Construction of Alandalus Townhouse is recorded as complete, with a registered completion date of October 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Alandalus Townhouse?
Alandalus Townhouse was 100% built at the site inspection on 5 October 2020. The site has been inspected 9 times since September 2017. The Land Department took 88 site photos at its inspections.
Is Alandalus Townhouse delayed?
The register lists construction as complete.
Who is building Alandalus Townhouse?
The registered developer is Jumeirah Golf Estates.
Which bank holds the escrow account for Alandalus Townhouse?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.