Alandalus construction progress

The register lists Alandalus in Jumeirah Golf Estates as complete, with a registered completion date of February 2019. Its last site inspection on record was in May 2019. The developer is Jumeirah Golf Estates.

100%

Built, at the site inspection of 12 May 2019

Construction complete

Registered completion date
February 2019
Construction started
August 2014
First registered
April 2015
Developer
Jumeirah Golf Estates
Units
215
Escrow bank
Emirates Islamic Bank
Name in Arabic
الأندلس
Project number
1652
Site inspections
11

Schedule

The register lists Alandalus as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20152016201720182019
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 May 2019

100%+0.9 pts

  • Alandalus construction site, inspection photo 1, 12 May 2019
  • Alandalus construction site, inspection photo 2, 12 May 2019
  • Alandalus construction site, inspection photo 3, 12 May 2019
  • Alandalus construction site, inspection photo 4, 12 May 2019

8 April 2019

99%+8.3 pts

  • Alandalus construction site, inspection photo 1, 8 April 2019
  • Alandalus construction site, inspection photo 2, 8 April 2019
  • Alandalus construction site, inspection photo 3, 8 April 2019
  • Alandalus construction site, inspection photo 4, 8 April 2019

2 January 2019

91%+13 pts

  • Alandalus construction site, inspection photo 1, 2 January 2019
  • Alandalus construction site, inspection photo 2, 2 January 2019
  • Alandalus construction site, inspection photo 3, 2 January 2019
  • Alandalus construction site, inspection photo 4, 2 January 2019

29 July 2018

77%+9.0 pts

  • Alandalus construction site, inspection photo 1, 29 July 2018
  • Alandalus construction site, inspection photo 2, 29 July 2018
  • Alandalus construction site, inspection photo 3, 29 July 2018
  • Alandalus construction site, inspection photo 4, 29 July 2018

26 April 2018

68%+13 pts

  • Alandalus construction site, inspection photo 1, 26 April 2018
  • Alandalus construction site, inspection photo 2, 26 April 2018
  • Alandalus construction site, inspection photo 3, 26 April 2018
  • Alandalus construction site, inspection photo 4, 26 April 2018

25 December 2017

55%+12 pts

  • Alandalus construction site, inspection photo 1, 25 December 2017
  • Alandalus construction site, inspection photo 2, 25 December 2017
  • Alandalus construction site, inspection photo 3, 25 December 2017
  • Alandalus construction site, inspection photo 4, 25 December 2017

1 October 2017

43%+14 pts

  • Alandalus construction site, inspection photo 1, 1 October 2017
  • Alandalus construction site, inspection photo 2, 1 October 2017
  • Alandalus construction site, inspection photo 3, 1 October 2017
  • Alandalus construction site, inspection photo 4, 1 October 2017

14 May 2017

29%+6.0 pts

  • Alandalus construction site, inspection photo 1, 14 May 2017
  • Alandalus construction site, inspection photo 2, 14 May 2017
  • Alandalus construction site, inspection photo 3, 14 May 2017
  • Alandalus construction site, inspection photo 4, 14 May 2017

9 March 2017

23%+5.0 pts

  • Alandalus construction site, inspection photo 1, 9 March 2017
  • Alandalus construction site, inspection photo 2, 9 March 2017
  • Alandalus construction site, inspection photo 3, 9 March 2017
  • Alandalus construction site, inspection photo 4, 9 March 2017

21 November 2016

18%+7.9 pts

  • Alandalus construction site, inspection photo 1, 21 November 2016
  • Alandalus construction site, inspection photo 2, 21 November 2016
  • Alandalus construction site, inspection photo 3, 21 November 2016
  • Alandalus construction site, inspection photo 4, 21 November 2016

All 107 site photos, by inspection date

Context

Jumeirah Golf Estates has 4 projects under construction, 49% built on average.

Own a unit in Alandalus?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Alandalus handover date?
Construction of Alandalus is recorded as complete, with a registered completion date of February 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Alandalus?
Alandalus was 100% built at the site inspection on 12 May 2019. The site has been inspected 11 times since November 2015. The Land Department took 107 site photos at its inspections.
Is Alandalus delayed?
The register lists construction as complete.
Who is building Alandalus?
The registered developer is Jumeirah Golf Estates.
Which bank holds the escrow account for Alandalus?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.