Skip to content

Lakeside construction progress

The register lists Lakeside in International Media Production Zone as complete, with a registered completion date of August 2014. Its last site inspection on record was in July 2014. The developer is The Waves.

100%

Built, at the site inspection of 14 July 2014

Construction complete

Registered completion date
August 2014
Construction started
March 2010
First registered
November 2008
Developer
The Waves
Units
1,967
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ليكسايد
Project number
436
Site inspections
5

Schedule

The register lists Lakeside as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2011201220132014
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 July 2014

90%+5.1 pts

  • Lakeside construction site, inspection photo 1, 14 July 2014
  • Lakeside construction site, inspection photo 2, 14 July 2014
  • Lakeside construction site, inspection photo 3, 14 July 2014
  • Lakeside construction site, inspection photo 4, 14 July 2014

5 March 2014

85%+9.5 pts

  • Lakeside construction site, inspection photo 1, 5 March 2014
  • Lakeside construction site, inspection photo 2, 5 March 2014
  • Lakeside construction site, inspection photo 3, 5 March 2014
  • Lakeside construction site, inspection photo 4, 5 March 2014

10 October 2013

76%+11 pts

  • Lakeside construction site, inspection photo 1, 10 October 2013
  • Lakeside construction site, inspection photo 2, 10 October 2013
  • Lakeside construction site, inspection photo 3, 10 October 2013
  • Lakeside construction site, inspection photo 4, 10 October 2013

6 February 2013

65%+50 pts

  • Lakeside construction site, inspection photo 1, 6 February 2013
  • Lakeside construction site, inspection photo 2, 6 February 2013
  • Lakeside construction site, inspection photo 3, 6 February 2013
  • Lakeside construction site, inspection photo 4, 6 February 2013

3 August 2010

15%

All 43 site photos, by inspection date

Context

International Media Production Zone has 15 projects under construction, 23% built on average.

Own a unit in Lakeside?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Lakeside handover date?
Construction of Lakeside is recorded as complete, with a registered completion date of August 2014. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Lakeside?
Lakeside was 100% built at the site inspection on 14 July 2014. The site has been inspected 5 times since August 2010. The Land Department took 43 site photos at its inspections.
Is Lakeside delayed?
The register lists construction as complete.
Who is building Lakeside?
The registered developer is The Waves.
Which bank holds the escrow account for Lakeside?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.