Zenith Residences construction photos

14 photos taken by Dubai Land Department engineers at 3 site inspections, newest first. The percentage is how much of Zenith Residences was built on the day of each visit.

7 October 202624% built

27 March 202611% built

20 May 20253.0% built

Back to Zenith Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.