The Maiden Residence construction photos
36 photos from 6 site inspections, newest first. The percentage is how much of The Maiden Residence was built on the day of each visit.
14 May 202673% built
10 March 202671% built
7 November 202541% built
8 July 202524% built
9 December 202412% built
22 August 20242.6% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.