Mayflower Residences construction photos

69 photos from 8 site inspections, newest first. The percentage is how much of Mayflower Residences was built on the day of each visit.

1 October 202696% built

16 April 202688% built

16 February 202668% built

6 November 202557% built

18 July 202537% built

18 April 202527% built

29 January 202511% built

27 September 20247.2% built

Back to Mayflower Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.