Equiti Tower construction progress
Equiti Tower in International City Phase 3 is 70% built at the Land Department inspection of December 2025. Developer B N H Real Estate Developer. Completion registered for August 2025.
70%
Built, at the Land Department site inspection of 31 December 2025
13 months past its registered completion date
- Completion date (Land Department)
- August 2025
- Finish at recent pace
- January 2027
- Construction started
- June 2024
- Registered with the Land Department
- March 2025
- Developer
- B N H Real Estate Developer
- Community
- International City Phase 3
- Units
- 88
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- برج ايكويتي
- Land Department project number
- 3185
- Land Department site inspections
- 2
Schedule
Equiti Tower was registered to complete in August 2025, 13 months ago, and is still under construction. Over the last year of inspections it has added about 2.3 points a month. Kept at that rate, the site would reach 100% around January 2027.
Site inspections
31 December 2025
70%+37 pts
28 August 2024
33%
Context
International City Phase 3 has 21 projects under construction, 30% built on average.
B N H Real Estate Developer has 2 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Equiti Tower?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Equiti Tower be completed?
- The completion date registered with the Dubai Land Department is August 2025. At the pace of its recent inspections the site would reach 100% around January 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Equiti Tower is built?
- 70%, measured at the Land Department site inspection on 31 December 2025. The Land Department engineers have inspected the site 2 times since August 2024.
- Is Equiti Tower delayed?
- Yes. Its registered completion date of August 2025 has passed and the Land Department still lists it as under construction.
- Who is building Equiti Tower?
- The registered developer is B N H Real Estate Developer. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Equiti Tower?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Equiti GardenAlso by B N H Real Estate Developer. 87%, Due December 2025, passed.
- Moonsa ResidencesNearby in International City Phase 3. 95%, Due August 2025, passed.
- The Maiden ResidenceNearby in International City Phase 3. 73%.
- Linden ResidencesNearby in International City Phase 3. 27%.
- Moonsa Residences 2Nearby in International City Phase 3. 1.0%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.