08 Life Residences construction photos

44 photos from 6 site inspections, newest first. The percentage is how much of 08 Life Residences was built on the day of each visit.

10 November 202678% built

26 August 202665% built

30 April 202648% built

22 December 202536% built

15 September 202524% built

25 March 20259.2% built

Back to 08 Life Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.