Lawnz Residence By Danube construction progress

The register lists Lawnz Residence By Danube in International City Phase 1 as complete, with a registered completion date of February 2022. Its last site inspection on record was in February 2022. The developer is Danube Properties Development.

100%

Built, at the site inspection of 1 February 2022

Construction complete

Registered completion date
February 2022
Construction started
September 2018
First registered
June 2018
Units
1,063
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
لونز رزيدنس من دانوب
Project number
2073
Site inspections
14

Schedule

The register lists Lawnz Residence By Danube as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2019202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 February 2022

100%+4.7 pts

  • Lawnz Residence By Danube construction site, inspection photo 1, 1 February 2022
  • Lawnz Residence By Danube construction site, inspection photo 2, 1 February 2022
  • Lawnz Residence By Danube construction site, inspection photo 3, 1 February 2022
  • Lawnz Residence By Danube construction site, inspection photo 4, 1 February 2022

12 January 2022

95%+10 pts

  • Lawnz Residence By Danube construction site, inspection photo 1, 12 January 2022
  • Lawnz Residence By Danube construction site, inspection photo 2, 12 January 2022
  • Lawnz Residence By Danube construction site, inspection photo 3, 12 January 2022
  • Lawnz Residence By Danube construction site, inspection photo 4, 12 January 2022

5 October 2021

85%+15 pts

  • Lawnz Residence By Danube construction site, inspection photo 1, 5 October 2021
  • Lawnz Residence By Danube construction site, inspection photo 2, 5 October 2021
  • Lawnz Residence By Danube construction site, inspection photo 3, 5 October 2021
  • Lawnz Residence By Danube construction site, inspection photo 4, 5 October 2021

8 July 2021

70%+12 pts

  • Lawnz Residence By Danube construction site, inspection photo 1, 8 July 2021
  • Lawnz Residence By Danube construction site, inspection photo 2, 8 July 2021
  • Lawnz Residence By Danube construction site, inspection photo 3, 8 July 2021
  • Lawnz Residence By Danube construction site, inspection photo 4, 8 July 2021

30 March 2021

58%+11 pts

  • Lawnz Residence By Danube construction site, inspection photo 1, 30 March 2021
  • Lawnz Residence By Danube construction site, inspection photo 2, 30 March 2021
  • Lawnz Residence By Danube construction site, inspection photo 3, 30 March 2021
  • Lawnz Residence By Danube construction site, inspection photo 4, 30 March 2021

4 January 2021

46%+6.4 pts

  • Lawnz Residence By Danube construction site, inspection photo 1, 4 January 2021
  • Lawnz Residence By Danube construction site, inspection photo 2, 4 January 2021
  • Lawnz Residence By Danube construction site, inspection photo 3, 4 January 2021
  • Lawnz Residence By Danube construction site, inspection photo 4, 4 January 2021

10 September 2020

40%+25 pts

  • Lawnz Residence By Danube construction site, inspection photo 1, 10 September 2020
  • Lawnz Residence By Danube construction site, inspection photo 2, 10 September 2020
  • Lawnz Residence By Danube construction site, inspection photo 3, 10 September 2020
  • Lawnz Residence By Danube construction site, inspection photo 4, 10 September 2020

2 June 2020

15%+5.2 pts

  • Lawnz Residence By Danube construction site, inspection photo 1, 2 June 2020
  • Lawnz Residence By Danube construction site, inspection photo 2, 2 June 2020
  • Lawnz Residence By Danube construction site, inspection photo 3, 2 June 2020
  • Lawnz Residence By Danube construction site, inspection photo 4, 2 June 2020

4 February 2020

10%+4.3 pts

  • Lawnz Residence By Danube construction site, inspection photo 1, 4 February 2020
  • Lawnz Residence By Danube construction site, inspection photo 2, 4 February 2020
  • Lawnz Residence By Danube construction site, inspection photo 3, 4 February 2020
  • Lawnz Residence By Danube construction site, inspection photo 4, 4 February 2020

7 November 2019

6.0%+1.2 pts

  • Lawnz Residence By Danube construction site, inspection photo 1, 7 November 2019
  • Lawnz Residence By Danube construction site, inspection photo 2, 7 November 2019
  • Lawnz Residence By Danube construction site, inspection photo 3, 7 November 2019
  • Lawnz Residence By Danube construction site, inspection photo 4, 7 November 2019

All 128 site photos, by inspection date

Context

International City Phase 1 has 3 projects under construction, 46% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Lawnz Residence By Danube?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Lawnz Residence By Danube handover date?
Construction of Lawnz Residence By Danube is recorded as complete, with a registered completion date of February 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Lawnz Residence By Danube?
Lawnz Residence By Danube was 100% built at the site inspection on 1 February 2022. The site has been inspected 14 times since December 2018. The Land Department took 128 site photos at its inspections.
Is Lawnz Residence By Danube delayed?
The register lists construction as complete.
Who is building Lawnz Residence By Danube?
The registered developer is Danube Properties Development. It has 23 other projects under construction in Dubai.
Which bank holds the escrow account for Lawnz Residence By Danube?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.