Longford Residences By Devan Real Estate Development construction progress
The registered completion date for Longford Residences By Devan Real Estate Development in International City Phase 1 is May 2028. At the last site inspection, in October 2026, it was 33% built. The developer is Devan Real Estate Development.
33%
Built, at the site inspection of 12 October 2026
Running behind its date
- Registered completion date
- May 2028
- Finish at recent pace
- August 2028
- Construction started
- June 2025
- First registered
- June 2025
- Developer
- Devan Real Estate Development
- Community
- International City Phase 1
- Units
- 280
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- لونجفورد ريزيدنسيز من ديفان للتطوير العقاري
- Project number
- 3688
- Site inspections
- 3
Schedule
Between March 2026 and October 2026 the site added about 3.1 points a month. At that rate it would finish around August 2028, more than three months after its registered date of May 2028.
Site inspections
12 October 2026
33%+20 pts
25 March 2026
12%+12 pts
21 April 2025
0%
Context
International City Phase 1 has 3 projects under construction, 46% built on average.
Own a unit in Longford Residences By Devan Real Estate Development?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Longford Residences By Devan Real Estate Development handover date?
- The registered completion date is May 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Longford Residences By Devan Real Estate Development?
- Longford Residences By Devan Real Estate Development was 33% built at the site inspection on 12 October 2026. The site has been inspected 3 times since April 2025. The Land Department took 19 site photos at its inspections.
- Is Longford Residences By Devan Real Estate Development delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
- Who is building Longford Residences By Devan Real Estate Development?
- The registered developer is Devan Real Estate Development.
- Which bank holds the escrow account for Longford Residences By Devan Real Estate Development?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Tomorrow Commercial TowerNearby in International City Phase 1. 70%, Due July 2026, passed.
- Lusin Residences By Ermax DevelopmentNearby in International City Phase 1. 35%, Due December 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)