Lawnz Residence By Danube construction photos

128 photos from 14 site inspections, newest first. The percentage is how much of Lawnz Residence By Danube was built on the day of each visit.

1 February 2022100% built

12 January 202295% built

5 October 202185% built

8 July 202170% built

30 March 202158% built

4 January 202146% built

10 September 202040% built

2 June 202015% built

4 February 202010% built

7 November 20196.0% built

2 October 20194.8% built

1 July 20191.5% built

18 March 20190.2% built

11 December 20180.2% built

Back to Lawnz Residence By Danube construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.