Valoria The Oasis construction progress
The registered completion date for Valoria The Oasis is December 2029. At the last site inspection, in July 2026, it was 1.1% built. The developer is Emaar Development.
1.1%
Built, at the site inspection of 7 July 2026
Running behind its date
- Registered completion date
- December 2029
- Finish at recent pace
- January 2077
- Construction started
- January 2026
- First registered
- December 2025
- Developer
- Emaar Development
- Units
- 257
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- فالوريا ذا أويسيس
- Project number
- 4277
- Site inspections
- 2
Schedule
Between December 2025 and July 2026 the site added about 0.2 points a month. At that rate it would finish around January 2077, more than three months after its registered date of December 2029.
Site inspections
7 July 2026
1.1%+1.1 pts
10 December 2025
0%
Context
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Valoria The Oasis?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Valoria The Oasis handover date?
- The registered completion date is December 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2077. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Valoria The Oasis?
- Valoria The Oasis was 1.1% built at the site inspection on 7 July 2026. The site has been inspected 2 times since December 2025. The Land Department took 4 site photos at its inspections.
- Is Valoria The Oasis delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2029.
- Who is building Valoria The Oasis?
- The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
- Which bank holds the escrow account for Valoria The Oasis?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.