Valoria The Oasis construction progress
Valoria The Oasis is 1.1% built at the Land Department inspection of July 2026. Developer Emaar Development. Completion registered for December 2029.
1.1%
Built, at the Land Department site inspection of 7 July 2026
Running behind its date
- Completion date (Land Department)
- December 2029
- Finish at recent pace
- January 2077
- Construction started
- January 2026
- Registered with the Land Department
- December 2025
- Developer
- Emaar Development
- Units
- 257
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- فالوريا ذا أويسيس
- Land Department project number
- 4277
- Land Department site inspections
- 2
Schedule
Between December 2025 and July 2026 the site added about 0.2 points a month. At that rate it would finish around January 2077, more than three months after the December 2029 date registered with the Land Department.
Site inspections
7 July 2026
1.1%+1.1 pts
10 December 2025
0%
Context
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Valoria The Oasis?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Valoria The Oasis be completed?
- The completion date registered with the Dubai Land Department is December 2029. At the pace of its recent inspections the site would reach 100% around January 2077. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Valoria The Oasis is built?
- 1.1%, measured at the Land Department site inspection on 7 July 2026. The Land Department engineers have inspected the site 2 times since December 2025.
- Is Valoria The Oasis delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2029.
- Who is building Valoria The Oasis?
- The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
- Which bank holds the escrow account for Valoria The Oasis?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- Deyaar ParkNearby in . 0%, Due December 2012, passed.
- Varazze TowerNearby in . 92%, Due February 2024, passed.
- Niki Lauda TowerNearby in . 0.4%.
- Champions Tower2Nearby in . 78%, Due October 2017, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.