Valoria The Oasis construction progress

Valoria The Oasis is 1.1% built at the Land Department inspection of July 2026. Developer Emaar Development. Completion registered for December 2029.

1.1%

Built, at the Land Department site inspection of 7 July 2026

Running behind its date

Completion date (Land Department)
December 2029
Finish at recent pace
January 2077
Construction started
January 2026
Registered with the Land Department
December 2025
Units
257
Escrow bank
First Abu Dhabi Bank
Name in Arabic
فالوريا ذا أويسيس
Land Department project number
4277
Land Department site inspections
2

Schedule

Between December 2025 and July 2026 the site added about 0.2 points a month. At that rate it would finish around January 2077, more than three months after the December 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

7 July 2026

1.1%+1.1 pts

  • Valoria The Oasis construction site, Land Department inspection photo 1, 7 July 2026
  • Valoria The Oasis construction site, Land Department inspection photo 2, 7 July 2026

10 December 2025

0%

  • Valoria The Oasis construction site, Land Department inspection photo 1, 10 December 2025
  • Valoria The Oasis construction site, Land Department inspection photo 2, 10 December 2025

All 4 site photos, by inspection date

Context

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Valoria The Oasis?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Valoria The Oasis be completed?
The completion date registered with the Dubai Land Department is December 2029. At the pace of its recent inspections the site would reach 100% around January 2077. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Valoria The Oasis is built?
1.1%, measured at the Land Department site inspection on 7 July 2026. The Land Department engineers have inspected the site 2 times since December 2025.
Is Valoria The Oasis delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2029.
Who is building Valoria The Oasis?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for Valoria The Oasis?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.