The Oasis - Palmiera Collective construction progress

The registered completion date for The Oasis - Palmiera Collective is February 2029. At the last site inspection, in June 2026, it was 1.3% built. The developer is Emaar Properties.

1.3%

Built, at the site inspection of 16 June 2026

Running behind its date

Registered completion date
February 2029
Finish at recent pace
July 2071
Construction started
January 2026
First registered
November 2025
Units
38
Escrow bank
Emirates Islamic Bank
Name in Arabic
ذا أويسيس - بالمييرا كولكتيف
Project number
4209
Site inspections
2

Schedule

Between November 2025 and June 2026 the site added about 0.2 points a month. At that rate it would finish around July 2071, more than three months after its registered date of February 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 June 2026

1.3%+1.3 pts

  • The Oasis - Palmiera Collective construction site, inspection photo 1, 16 June 2026
  • The Oasis - Palmiera Collective construction site, inspection photo 2, 16 June 2026
  • The Oasis - Palmiera Collective construction site, inspection photo 3, 16 June 2026

6 November 2025

0%

  • The Oasis - Palmiera Collective construction site, inspection photo 1, 6 November 2025
  • The Oasis - Palmiera Collective construction site, inspection photo 2, 6 November 2025
  • The Oasis - Palmiera Collective construction site, inspection photo 3, 6 November 2025

All 6 site photos, by inspection date

Context

Emaar Properties has 7 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Oasis - Palmiera Collective?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Oasis - Palmiera Collective handover date?
The registered completion date is February 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2071. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Oasis - Palmiera Collective?
The Oasis - Palmiera Collective was 1.3% built at the site inspection on 16 June 2026. The site has been inspected 2 times since November 2025. The Land Department took 6 site photos at its inspections.
Is The Oasis - Palmiera Collective delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2029.
Who is building The Oasis - Palmiera Collective?
The registered developer is Emaar Properties. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for The Oasis - Palmiera Collective?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.