Serro 2 The Heights construction progress

The registered completion date for Serro 2 The Heights is May 2030. At the last site inspection, in June 2026, it was 0.5% built. The developer is Emaar Development.

0.5%

Built, at the site inspection of 9 June 2026

Running behind its date

Registered completion date
May 2030
Finish at recent pace
December 2135
Construction started
April 2026
First registered
November 2025
Units
397
Escrow bank
First Abu Dhabi Bank
Name in Arabic
سرو 2 ذا هايتس
Project number
4238
Site inspections
2

Schedule

Between November 2025 and June 2026 the site added about 0.1 points a month. At that rate it would finish around December 2135, more than three months after its registered date of May 2030.

0%25%50%75%100%20262027202820292030
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 June 2026

0.5%+0.5 pts

  • Serro 2 The Heights construction site, inspection photo 1, 9 June 2026
  • Serro 2 The Heights construction site, inspection photo 2, 9 June 2026
  • Serro 2 The Heights construction site, inspection photo 3, 9 June 2026

20 November 2025

0%

  • Serro 2 The Heights construction site, inspection photo 1, 20 November 2025
  • Serro 2 The Heights construction site, inspection photo 2, 20 November 2025
  • Serro 2 The Heights construction site, inspection photo 3, 20 November 2025

All 6 site photos, by inspection date

Context

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Serro 2 The Heights?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Serro 2 The Heights handover date?
The registered completion date is May 2030. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2135. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Serro 2 The Heights?
Serro 2 The Heights was 0.5% built at the site inspection on 9 June 2026. The site has been inspected 2 times since November 2025. The Land Department took 6 site photos at its inspections.
Is Serro 2 The Heights delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2030.
Who is building Serro 2 The Heights?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for Serro 2 The Heights?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.