Avarra By Palace construction progress
The registered completion date for Avarra By Palace is June 2031. At the last site inspection, in June 2026, it was 0.1% built. The developer is Emaar Development.
0.1%
Built, at the site inspection of 10 June 2026
Running behind its date
- Registered completion date
- June 2031
- Finish at recent pace
- January 2724
- Construction started
- May 2026
- First registered
- November 2025
- Developer
- Emaar Development
- Units
- 694
- Escrow bank
- Emirates NBD
- Name in Arabic
- افارا باي بالاس
- Project number
- 4227
- Site inspections
- 2
Schedule
Between November 2025 and June 2026 the site added about 0.0 points a month. At that rate it would finish around January 2724, more than three months after its registered date of June 2031.
Site inspections
10 June 2026
0.1%+0.1 pts
18 November 2025
0%
Context
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Avarra By Palace?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Avarra By Palace handover date?
- The registered completion date is June 2031. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2724. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Avarra By Palace?
- Avarra By Palace was 0.1% built at the site inspection on 10 June 2026. The site has been inspected 2 times since November 2025. The Land Department took 4 site photos at its inspections.
- Is Avarra By Palace delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2031.
- Who is building Avarra By Palace?
- The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
- Which bank holds the escrow account for Avarra By Palace?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

