Eden House The Park construction progress

Eden House The Park in Dubai Water Canal is 64% built at the Land Department inspection of July 2026. Developer H & H Development. Completion registered for February 2027.

64%

Built, at the Land Department site inspection of 30 July 2026

Running behind its date

Completion date (Land Department)
February 2027
Finish at recent pace
June 2027
Construction started
November 2024
Registered with the Land Department
November 2024
Developer
H & H Development
Units
466
Escrow bank
Emirates NBD
Name in Arabic
ايدن هاوس ذا بارك
Land Department project number
3382
Land Department site inspections
5

Schedule

Between October 2025 and July 2026 the site added about 3.5 points a month. At that rate it would finish around June 2027, more than three months after the February 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 July 2026

64%+20 pts

  • Eden House The Park construction site, Land Department inspection photo 1, 30 July 2026
  • Eden House The Park construction site, Land Department inspection photo 2, 30 July 2026
  • Eden House The Park construction site, Land Department inspection photo 3, 30 July 2026
  • Eden House The Park construction site, Land Department inspection photo 4, 30 July 2026

30 March 2026

43%+11 pts

  • Eden House The Park construction site, Land Department inspection photo 1, 30 March 2026
  • Eden House The Park construction site, Land Department inspection photo 2, 30 March 2026
  • Eden House The Park construction site, Land Department inspection photo 3, 30 March 2026
  • Eden House The Park construction site, Land Department inspection photo 4, 30 March 2026

29 October 2025

32%+21 pts

  • Eden House The Park construction site, Land Department inspection photo 1, 29 October 2025
  • Eden House The Park construction site, Land Department inspection photo 2, 29 October 2025
  • Eden House The Park construction site, Land Department inspection photo 3, 29 October 2025
  • Eden House The Park construction site, Land Department inspection photo 4, 29 October 2025

6 May 2025

11%+9.3 pts

  • Eden House The Park construction site, Land Department inspection photo 1, 6 May 2025
  • Eden House The Park construction site, Land Department inspection photo 2, 6 May 2025
  • Eden House The Park construction site, Land Department inspection photo 3, 6 May 2025
  • Eden House The Park construction site, Land Department inspection photo 4, 6 May 2025

18 November 2024

1.9%

  • Eden House The Park construction site, Land Department inspection photo 1, 18 November 2024
  • Eden House The Park construction site, Land Department inspection photo 2, 18 November 2024
  • Eden House The Park construction site, Land Department inspection photo 3, 18 November 2024

All 41 site photos, by inspection date

Context

Dubai Water Canal has 10 projects under construction, 37% built on average.

Own a unit in Eden House The Park?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Eden House The Park be completed?
The completion date registered with the Dubai Land Department is February 2027. At the pace of its recent inspections the site would reach 100% around June 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Eden House The Park is built?
64%, measured at the Land Department site inspection on 30 July 2026. The Land Department engineers have inspected the site 5 times since November 2024.
Is Eden House The Park delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
Who is building Eden House The Park?
The registered developer is H & H Development.
Which bank holds the escrow account for Eden House The Park?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.