Eden House The Park construction progress

The registered completion date for Eden House The Park in Dubai Water Canal is February 2027. At the last site inspection, in July 2026, it was 64% built. The developer is H & H Development.

64%

Built, at the site inspection of 30 July 2026

Running behind its date

Registered completion date
February 2027
Finish at recent pace
June 2027
Construction started
November 2024
First registered
November 2024
Developer
H & H Development
Units
466
Escrow bank
Emirates NBD
Name in Arabic
ايدن هاوس ذا بارك
Project number
3382
Site inspections
5

Schedule

Between October 2025 and July 2026 the site added about 3.5 points a month. At that rate it would finish around June 2027, more than three months after its registered date of February 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 July 2026

64%+20 pts

  • Eden House The Park construction site, inspection photo 1, 30 July 2026
  • Eden House The Park construction site, inspection photo 2, 30 July 2026
  • Eden House The Park construction site, inspection photo 3, 30 July 2026
  • Eden House The Park construction site, inspection photo 4, 30 July 2026

30 March 2026

43%+11 pts

  • Eden House The Park construction site, inspection photo 1, 30 March 2026
  • Eden House The Park construction site, inspection photo 2, 30 March 2026
  • Eden House The Park construction site, inspection photo 3, 30 March 2026
  • Eden House The Park construction site, inspection photo 4, 30 March 2026

29 October 2025

32%+21 pts

  • Eden House The Park construction site, inspection photo 1, 29 October 2025
  • Eden House The Park construction site, inspection photo 2, 29 October 2025
  • Eden House The Park construction site, inspection photo 3, 29 October 2025
  • Eden House The Park construction site, inspection photo 4, 29 October 2025

6 May 2025

11%+9.3 pts

  • Eden House The Park construction site, inspection photo 1, 6 May 2025
  • Eden House The Park construction site, inspection photo 2, 6 May 2025
  • Eden House The Park construction site, inspection photo 3, 6 May 2025
  • Eden House The Park construction site, inspection photo 4, 6 May 2025

18 November 2024

1.9%

  • Eden House The Park construction site, inspection photo 1, 18 November 2024
  • Eden House The Park construction site, inspection photo 2, 18 November 2024
  • Eden House The Park construction site, inspection photo 3, 18 November 2024

All 41 site photos, by inspection date

Context

Dubai Water Canal has 11 projects under construction, 38% built on average.

Own a unit in Eden House The Park?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Eden House The Park handover date?
The registered completion date is February 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Eden House The Park?
Eden House The Park was 64% built at the site inspection on 30 July 2026. The site has been inspected 5 times since November 2024. The Land Department took 41 site photos at its inspections.
Is Eden House The Park delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
Who is building Eden House The Park?
The registered developer is H & H Development.
Which bank holds the escrow account for Eden House The Park?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.