Eden House The Park construction progress
Eden House The Park in Dubai Water Canal is 64% built at the Land Department inspection of July 2026. Developer H & H Development. Completion registered for February 2027.
64%
Built, at the Land Department site inspection of 30 July 2026
Running behind its date
- Completion date (Land Department)
- February 2027
- Finish at recent pace
- June 2027
- Construction started
- November 2024
- Registered with the Land Department
- November 2024
- Developer
- H & H Development
- Community
- Dubai Water Canal
- Units
- 466
- Escrow bank
- Emirates NBD
- Name in Arabic
- ايدن هاوس ذا بارك
- Land Department project number
- 3382
- Land Department site inspections
- 5
Schedule
Between October 2025 and July 2026 the site added about 3.5 points a month. At that rate it would finish around June 2027, more than three months after the February 2027 date registered with the Land Department.
Site inspections
30 July 2026
64%+20 pts
30 March 2026
43%+11 pts
29 October 2025
32%+21 pts
6 May 2025
11%+9.3 pts
18 November 2024
1.9%
Context
Dubai Water Canal has 10 projects under construction, 37% built on average.
Own a unit in Eden House The Park?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Eden House The Park be completed?
- The completion date registered with the Dubai Land Department is February 2027. At the pace of its recent inspections the site would reach 100% around June 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Eden House The Park is built?
- 64%, measured at the Land Department site inspection on 30 July 2026. The Land Department engineers have inspected the site 5 times since November 2024.
- Is Eden House The Park delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
- Who is building Eden House The Park?
- The registered developer is H & H Development.
- Which bank holds the escrow account for Eden House The Park?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac CityNearby in Dubai Water Canal. 73%, Due December 2025, passed.
- Cavalli CoutureNearby in Dubai Water Canal. 20%, Due May 2025, passed.
- One CanalNearby in Dubai Water Canal. 77%.
- Casa CanalNearby in Dubai Water Canal. 38%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)