Damac City 2 construction progress

No completion date is registered for Damac City 2 in Dubai Water Canal yet. At the last site inspection, in November 2026, it was 14% built. The developer is Pinnacle Real Estate Developments.

14%

Built, at the site inspection of 4 November 2026

Finish at recent pace
September 2032
Construction started
June 2024
First registered
April 2024
Developer
Pinnacle Real Estate Developments
Units
731
Escrow bank
Emirates NBD
Name in Arabic
داماك سيتي 2
Project number
3001
Site inspections
5

Schedule

Since December 2025 Damac City 2 has added about 1.2 points a month. At that rate the site reaches 100% around September 2032. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

4 November 2026

14%+8.1 pts

  • Damac City 2 construction site, inspection photo 1, 4 November 2026
  • Damac City 2 construction site, inspection photo 2, 4 November 2026
  • Damac City 2 construction site, inspection photo 3, 4 November 2026
  • Damac City 2 construction site, inspection photo 4, 4 November 2026

9 April 2026

5.7%+4.4 pts

  • Damac City 2 construction site, inspection photo 1, 9 April 2026
  • Damac City 2 construction site, inspection photo 2, 9 April 2026
  • Damac City 2 construction site, inspection photo 3, 9 April 2026

25 December 2025

1.3%+1.2 pts

  • Damac City 2 construction site, inspection photo 1, 25 December 2025
  • Damac City 2 construction site, inspection photo 2, 25 December 2025
  • Damac City 2 construction site, inspection photo 3, 25 December 2025
  • Damac City 2 construction site, inspection photo 4, 25 December 2025

13 May 2025

0.1%+0.1 pts

  • Damac City 2 construction site, inspection photo 1, 13 May 2025
  • Damac City 2 construction site, inspection photo 2, 13 May 2025
  • Damac City 2 construction site, inspection photo 3, 13 May 2025
  • Damac City 2 construction site, inspection photo 4, 13 May 2025

25 March 2024

0%

  • Damac City 2 construction site, inspection photo 1, 25 March 2024
  • Damac City 2 construction site, inspection photo 2, 25 March 2024

All 19 site photos, by inspection date

Context

Dubai Water Canal has 11 projects under construction, 38% built on average.

Own a unit in Damac City 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac City 2 handover date?
No completion date is on record for Damac City 2 yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Damac City 2?
Damac City 2 was 14% built at the site inspection on 4 November 2026. The site has been inspected 5 times since March 2024. The Land Department took 19 site photos at its inspections.
Who is building Damac City 2?
The registered developer is Pinnacle Real Estate Developments.
Which bank holds the escrow account for Damac City 2?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.