Casa Ahs construction progress
Casa Ahs in Dubai Water Canal is 16% built at the Land Department inspection of September 2026. Developer Ahs Canal Three Development. Completion registered for May 2027.
16%
Built, at the Land Department site inspection of 24 September 2026
Running behind its date
- Completion date (Land Department)
- May 2027
- Finish at recent pace
- February 2033
- Construction started
- June 2025
- Registered with the Land Department
- April 2025
- Developer
- Ahs Canal Three Development
- Community
- Dubai Water Canal
- Units
- 32
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- كاسا ا يه اتش ا س
- Land Department project number
- 3589
- Land Department site inspections
- 3
Schedule
Between March 2026 and September 2026 the site added about 1.1 points a month. At that rate it would finish around February 2033, more than three months after the May 2027 date registered with the Land Department.
Site inspections
24 September 2026
16%+6.9 pts
17 March 2026
9.2%+7.2 pts
14 March 2025
1.9%
Context
Dubai Water Canal has 10 projects under construction, 37% built on average.
Own a unit in Casa Ahs?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Casa Ahs be completed?
- The completion date registered with the Dubai Land Department is May 2027. At the pace of its recent inspections the site would reach 100% around February 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Casa Ahs is built?
- 16%, measured at the Land Department site inspection on 24 September 2026. The Land Department engineers have inspected the site 3 times since March 2025.
- Is Casa Ahs delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
- Who is building Casa Ahs?
- The registered developer is Ahs Canal Three Development.
- Which bank holds the escrow account for Casa Ahs?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac CityNearby in Dubai Water Canal. 73%, Due December 2025, passed.
- Cavalli CoutureNearby in Dubai Water Canal. 20%, Due May 2025, passed.
- One CanalNearby in Dubai Water Canal. 77%.
- Casa CanalNearby in Dubai Water Canal. 38%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.