Skyhills Astra By Hre construction progress

The registered completion date for Skyhills Astra By Hre in Dubai Science Park is June 2028. At the last site inspection, in November 2026, it was 51% built. The developer is Hre Real Estate Development.

51%

Built, at the site inspection of 13 November 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
September 2030
Construction started
January 2025
First registered
January 2025
Units
1,911
Escrow bank
Sharjah Islamic Bank
Name in Arabic
سكاي هيلز استرا من اتش ار اي
Project number
3480
Site inspections
6

Schedule

Between January 2026 and November 2026 the site added about 1.1 points a month. At that rate it would finish around September 2030, more than three months after its registered date of June 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 November 2026

51%+3.6 pts

  • Skyhills Astra By Hre construction site, inspection photo 1, 13 November 2026
  • Skyhills Astra By Hre construction site, inspection photo 2, 13 November 2026
  • Skyhills Astra By Hre construction site, inspection photo 3, 13 November 2026
  • Skyhills Astra By Hre construction site, inspection photo 4, 13 November 2026

30 July 2026

47%+5.0 pts

  • Skyhills Astra By Hre construction site, inspection photo 1, 30 July 2026
  • Skyhills Astra By Hre construction site, inspection photo 2, 30 July 2026
  • Skyhills Astra By Hre construction site, inspection photo 3, 30 July 2026
  • Skyhills Astra By Hre construction site, inspection photo 4, 30 July 2026

22 April 2026

42%+2.1 pts

  • Skyhills Astra By Hre construction site, inspection photo 1, 22 April 2026
  • Skyhills Astra By Hre construction site, inspection photo 2, 22 April 2026
  • Skyhills Astra By Hre construction site, inspection photo 3, 22 April 2026
  • Skyhills Astra By Hre construction site, inspection photo 4, 22 April 2026

12 January 2026

40%+5.9 pts

  • Skyhills Astra By Hre construction site, inspection photo 1, 12 January 2026
  • Skyhills Astra By Hre construction site, inspection photo 2, 12 January 2026
  • Skyhills Astra By Hre construction site, inspection photo 3, 12 January 2026
  • Skyhills Astra By Hre construction site, inspection photo 4, 12 January 2026

24 September 2025

34%+1.3 pts

  • Skyhills Astra By Hre construction site, inspection photo 1, 24 September 2025
  • Skyhills Astra By Hre construction site, inspection photo 2, 24 September 2025
  • Skyhills Astra By Hre construction site, inspection photo 3, 24 September 2025
  • Skyhills Astra By Hre construction site, inspection photo 4, 24 September 2025

16 January 2025

33%

  • Skyhills Astra By Hre construction site, inspection photo 1, 16 January 2025
  • Skyhills Astra By Hre construction site, inspection photo 2, 16 January 2025
  • Skyhills Astra By Hre construction site, inspection photo 3, 16 January 2025
  • Skyhills Astra By Hre construction site, inspection photo 4, 16 January 2025

All 50 site photos, by inspection date

Context

Dubai Science Park has 10 projects under construction, 43% built on average.

Hre Real Estate Development has 5 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Skyhills Astra By Hre?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Skyhills Astra By Hre handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Skyhills Astra By Hre?
Skyhills Astra By Hre was 51% built at the site inspection on 13 November 2026. The site has been inspected 6 times since January 2025. The Land Department took 50 site photos at its inspections.
Is Skyhills Astra By Hre delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Skyhills Astra By Hre?
The registered developer is Hre Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Skyhills Astra By Hre?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.