Skyhills Astra By Hre construction progress

Skyhills Astra By Hre in Dubai Science Park is 47% built at the Land Department inspection of July 2026. Developer Hre Real Estate Development. Completion registered for June 2028.

47%

Built, at the Land Department site inspection of 30 July 2026

Running behind its date

Completion date (Land Department)
June 2028
Finish at recent pace
January 2030
Construction started
January 2025
Registered with the Land Department
January 2025
Units
1,911
Escrow bank
Sharjah Islamic Bank
Name in Arabic
سكاي هيلز استرا من اتش ار اي
Land Department project number
3480
Land Department site inspections
5

Schedule

Between September 2025 and July 2026 the site added about 1.3 points a month. At that rate it would finish around January 2030, more than three months after the June 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 July 2026

47%+5.0 pts

  • Skyhills Astra By Hre construction site, Land Department inspection photo 1, 30 July 2026
  • Skyhills Astra By Hre construction site, Land Department inspection photo 2, 30 July 2026
  • Skyhills Astra By Hre construction site, Land Department inspection photo 3, 30 July 2026
  • Skyhills Astra By Hre construction site, Land Department inspection photo 4, 30 July 2026

22 April 2026

42%+2.1 pts

  • Skyhills Astra By Hre construction site, Land Department inspection photo 1, 22 April 2026
  • Skyhills Astra By Hre construction site, Land Department inspection photo 2, 22 April 2026
  • Skyhills Astra By Hre construction site, Land Department inspection photo 3, 22 April 2026
  • Skyhills Astra By Hre construction site, Land Department inspection photo 4, 22 April 2026

12 January 2026

40%+5.9 pts

  • Skyhills Astra By Hre construction site, Land Department inspection photo 1, 12 January 2026
  • Skyhills Astra By Hre construction site, Land Department inspection photo 2, 12 January 2026
  • Skyhills Astra By Hre construction site, Land Department inspection photo 3, 12 January 2026
  • Skyhills Astra By Hre construction site, Land Department inspection photo 4, 12 January 2026

24 September 2025

34%+1.3 pts

  • Skyhills Astra By Hre construction site, Land Department inspection photo 1, 24 September 2025
  • Skyhills Astra By Hre construction site, Land Department inspection photo 2, 24 September 2025
  • Skyhills Astra By Hre construction site, Land Department inspection photo 3, 24 September 2025
  • Skyhills Astra By Hre construction site, Land Department inspection photo 4, 24 September 2025

16 January 2025

33%

  • Skyhills Astra By Hre construction site, Land Department inspection photo 1, 16 January 2025
  • Skyhills Astra By Hre construction site, Land Department inspection photo 2, 16 January 2025
  • Skyhills Astra By Hre construction site, Land Department inspection photo 3, 16 January 2025
  • Skyhills Astra By Hre construction site, Land Department inspection photo 4, 16 January 2025

All 35 site photos, by inspection date

Context

Dubai Science Park has 10 projects under construction, 40% built on average.

Hre Real Estate Development has 5 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Skyhills Astra By Hre?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Skyhills Astra By Hre be completed?
The completion date registered with the Dubai Land Department is June 2028. At the pace of its recent inspections the site would reach 100% around January 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Skyhills Astra By Hre is built?
47%, measured at the Land Department site inspection on 30 July 2026. The Land Department engineers have inspected the site 5 times since January 2025.
Is Skyhills Astra By Hre delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Skyhills Astra By Hre?
The registered developer is Hre Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Skyhills Astra By Hre?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.