The Mural construction progress

The registered completion date for The Mural in Dubai Maritime City is July 2028. At the last site inspection, in October 2026, it was 17% built. The developer is The Mural Real Estate.

17%

Built, at the site inspection of 1 October 2026

Running behind its date

Registered completion date
July 2028
Finish at recent pace
July 2031
Construction started
October 2025
First registered
April 2025
Developer
The Mural Real Estate
Units
268
Escrow bank
Commercial Bank of Dubai
Name in Arabic
ذا ميورال
Project number
3650
Site inspections
6

Schedule

Between October 2025 and October 2026 the site added about 1.4 points a month. At that rate it would finish around July 2031, more than three months after its registered date of July 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 October 2026

17%+8.4 pts

  • The Mural construction site, inspection photo 1, 1 October 2026
  • The Mural construction site, inspection photo 2, 1 October 2026
  • The Mural construction site, inspection photo 3, 1 October 2026
  • The Mural construction site, inspection photo 4, 1 October 2026

7 May 2026

8.2%+1.8 pts

  • The Mural construction site, inspection photo 1, 7 May 2026
  • The Mural construction site, inspection photo 2, 7 May 2026
  • The Mural construction site, inspection photo 3, 7 May 2026
  • The Mural construction site, inspection photo 4, 7 May 2026

28 January 2026

6.4%+6.0 pts

  • The Mural construction site, inspection photo 1, 28 January 2026
  • The Mural construction site, inspection photo 2, 28 January 2026
  • The Mural construction site, inspection photo 3, 28 January 2026
  • The Mural construction site, inspection photo 4, 28 January 2026

24 October 2025

0.4%+0.1 pts

  • The Mural construction site, inspection photo 1, 24 October 2025
  • The Mural construction site, inspection photo 2, 24 October 2025
  • The Mural construction site, inspection photo 3, 24 October 2025

29 July 2025

0.3%+0.3 pts

  • The Mural construction site, inspection photo 1, 29 July 2025
  • The Mural construction site, inspection photo 2, 29 July 2025
  • The Mural construction site, inspection photo 3, 29 July 2025
  • The Mural construction site, inspection photo 4, 29 July 2025

3 April 2025

0%

  • The Mural construction site, inspection photo 1, 3 April 2025
  • The Mural construction site, inspection photo 2, 3 April 2025

All 26 site photos, by inspection date

Context

Dubai Maritime City has 23 projects under construction, 32% built on average.

Own a unit in The Mural?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Mural handover date?
The registered completion date is July 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Mural?
The Mural was 17% built at the site inspection on 1 October 2026. The site has been inspected 6 times since April 2025. The Land Department took 26 site photos at its inspections.
Is The Mural delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2028.
Who is building The Mural?
The registered developer is The Mural Real Estate.
Which bank holds the escrow account for The Mural?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.