26 photos from 6 site inspections, newest first. The percentage is how much of The Mural was built on the day of each visit.

1 October 202617% built

7 May 20268.2% built

28 January 20266.4% built

24 October 20250.4% built

29 July 20250.3% built

3 April 20250% built

Back to The Mural construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.