Orise construction progress
Orise in Dubai Maritime City is 8.6% built at the Land Department inspection of May 2026. Developer Orise Residences Real Estate Development. Completion registered for November 2027.
8.6%
Built, at the Land Department site inspection of 7 May 2026
Running behind its date
- Completion date (Land Department)
- November 2027
- Finish at recent pace
- November 2035
- Construction started
- February 2025
- Registered with the Land Department
- December 2024
- Developer
- Orise Residences Real Estate Development
- Community
- Dubai Maritime City
- Units
- 534
- Escrow bank
- Emirates NBD
- Name in Arabic
- أورايز
- Land Department project number
- 3425
- Land Department site inspections
- 6
Schedule
Between July 2025 and May 2026 the site added about 0.8 points a month. At that rate it would finish around November 2035, more than three months after the November 2027 date registered with the Land Department.
Site inspections
7 May 2026
8.6%+2.6 pts
28 January 2026
6.0%+1.8 pts
24 October 2025
4.2%+3.2 pts
22 July 2025
1.0%+1.0 pts
14 April 2025
0%+0.0 pts
25 November 2024
0%
Context
Dubai Maritime City has 23 projects under construction, 29% built on average.
Own a unit in Orise?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Orise be completed?
- The completion date registered with the Dubai Land Department is November 2027. At the pace of its recent inspections the site would reach 100% around November 2035. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Orise is built?
- 8.6%, measured at the Land Department site inspection on 7 May 2026. The Land Department engineers have inspected the site 6 times since November 2024.
- Is Orise delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
- Who is building Orise?
- The registered developer is Orise Residences Real Estate Development.
- Which bank holds the escrow account for Orise?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Harbour LightsNearby in Dubai Maritime City. 64%, Due May 2027.
- Mar CasaNearby in Dubai Maritime City. 56%, Due October 2026.
- Aria By BeyondNearby in Dubai Maritime City. 85%, Due January 2026, passed.
- Coral ReefNearby in Dubai Maritime City. 33%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)